Pull Planning in Construction: How GCs Run a Session

Pull planning in construction means working backward from a milestone with trade foremen. How to run a session, track PPC and keep trades committed.

Published
Reading time
7 min read
Author
Adam HicksCooperBuild AI
On this page9 sections
  1. What is pull planning in construction?
  2. How is pull planning different from a CPM schedule?
  3. Who should be in a pull planning session?
  4. How do you run a pull planning session step by step?
  5. What happens after the pull planning session?
  6. Why do trades push back on pull planning?
  7. Do you need software for pull planning?
  8. FAQ
  9. What is pull planning in construction?
  10. Is pull planning the same as the Last Planner System?
  11. How long should a pull planning session take?
  12. What is percent plan complete (PPC)?
  13. Who should attend a pull planning meeting?
  14. Keep pull plan commitments from getting lost

By Adam Hicks, CooperBuild AI · November 14, 2026

Pull planning in construction is a scheduling method where the GC and the trade foremen start at a milestone and work backward, with each trade saying what it needs from the trade before it to start on time. The people doing the work set the sequence and the handoffs, so the plan reflects real crew durations and the team actually commits to it.

It's the "should" step of the Last Planner System, and it feeds your look-ahead and weekly work plan. This guide covers how a session runs, who should be in the room, what to do after the sticky notes come off the wall and the mistakes that make trades call it a waste of time.

What is pull planning in construction?

Pull planning is backward scheduling done as a team. Instead of a scheduler pushing dates forward from today ("framing done, then rough-in, then drywall"), the team picks a milestone, such as dry-in, ceiling close-in or turnover of a floor, and asks: what has to be done right before this? Then what has to be done before that? The work is "pulled" by the next trade's need, not pushed by whoever is free.

The Lean Construction Institute describes pull planning (opens in a new tab) as a method where people, materials, information and equipment arrive only when and where they're needed to keep work flowing. In LCI's Last Planner System, pull planning sits alongside milestone planning as the "should" conversation. Make-ready planning covers what "can" be done, weekly work planning covers what "will" be done, daily huddles track what "did" get done, and a weekly review covers what the team can "learn."

How is pull planning different from a CPM schedule?

It doesn't replace your master schedule. The CPM schedule (often built in P6 or Microsoft Project) sets the contract milestones and the overall logic. A pull plan zooms into one phase between two milestones and works out the handoffs with the people who'll do the work.

The difference is who builds it and how. A CPM schedule is usually built by a scheduler or PM and handed to the trades. A pull plan is built in the room with the trade foremen, so durations come from the crews, and every handoff gets a name attached. When a trade says "I need the ceiling grid inspected before I can hang devices," that dependency is on the board and both trades heard it.

Who should be in a pull planning session?

Bring the people closest to the work who can make real commitments. LCI calls them the "last planners": the people with the authority to make decisions about their own work and to make reliable promises for their discipline.

  • Superintendent: usually runs the session and owns the plan afterward.
  • Trade foremen or field leads: not just the sub's PM. The foreman knows crew size and real production rates.
  • GC project manager: to flag submittals, RFIs, procurement and owner decisions that could hold up the work.
  • Key suppliers or designers, when needed: for long-lead items or open design questions.

Keep it to the trades that touch the phase. A pull plan for interior finishes doesn't need the site work sub.

How do you run a pull planning session step by step?

Here's a practical flow you can run for one phase in a single session, often an hour or two.

  1. Set the milestone and the window. Put the end milestone on the right side of the wall or board (for example "Level 2 ready for ceiling close-in") with its date. Mark the start date on the left.
  2. Each trade writes its tasks. Every trade gets its own sticky color. One task per note: what, where, crew size and duration in days. Keep tasks small enough to finish in a week or less.
  3. Pull backward from the milestone. Start at the milestone and ask which tasks must be finished right before it. Each trade places its notes and says what it needs from the previous trade to start: a completed area, an inspection, material on site or an answer from the design team.
  4. Talk through every handoff. This is the real value of the session. The trade receiving the work says what "done" means to them. The trade handing off agrees or pushes back. Gaps and overlaps show up here, not three weeks later in the field.
  5. Find the gap and close it. If the plan doesn't fit the window, the team works out how to recover: resequence areas, add a crew, split a task, or pull an inspection forward. Don't just shrink every duration.
  6. Capture constraints. Every "we can't start until..." becomes a constraint with an owner and a due date: a submittal approval, a delivery, an RFI answer, a permit inspection.
  7. Photograph and transcribe it. Before anyone leaves, take photos and get the plan into whatever the field uses daily, whether that's your look-ahead spreadsheet or your project software.

What happens after the pull planning session?

The session is the easy part. The plan only works if it flows into weekly execution.

  • Feed the look-ahead. Move pull plan tasks into your 3-week look-ahead schedule and review constraints every week.
  • Make work ready. The PM and super chase down every constraint before the task's start date. If a constraint can't be cleared, the task doesn't go on next week's plan.
  • Make weekly promises. In the weekly coordination meeting, each foreman commits to specific tasks for the coming week.
  • Run daily huddles. A short morning stand-up keeps the week's plan honest and surfaces problems the same day. One PM in an r/ConstructionManagers thread on TAKT and pull planning (opens in a new tab) said weekly coordination meetings alone "are not enough" when the super skips daily huddles.
  • Track percent plan complete (PPC). At the end of the week, count planned tasks finished as promised divided by total planned tasks. For each miss, log the reason (material late, area not ready, crew pulled, design question). The reasons are where the improvement comes from.

LCI says that on traditional projects only about 54% of the work planned for a given week gets completed on schedule, which is why tracking PPC and reasons for variance matters more than the sticky notes.

Why do trades push back on pull planning?

Pull planning gets a bad reputation when it turns into a long meeting with nothing after it. A superintendent in an r/ConstructionManagers thread (opens in a new tab) wrote that co-workers felt pull plan meetings "can be a waste of time or frustrate people." Common causes:

  • The GC brings a finished schedule and asks trades to sign off. That's not pull planning. Trades need to set their own durations and handoffs.
  • The wrong people show up. A sub's office PM can't commit crews the way a foreman can.
  • The plan dies on the wall. If nobody transcribes it and reviews it weekly, the next session feels pointless.
  • Constraints aren't owned. A constraint without a name and a date won't get cleared.
  • The jargon. One PM in the TAKT thread calls them "phase meetings" to "reduce the stigma from the trades." Use whatever name gets people in the room.

Do you need software for pull planning?

No. Sticky notes on a wall or a whiteboard work fine, and many teams prefer the room for the conversation. Software helps after the session: keeping the plan, constraints and weekly commitments in one place where the whole team can see them, especially on jobs with several areas or remote trade partners.

What matters most is that constraints and commitments don't get lost in texts and side conversations. Keep a single list of who owes what by when, review it in your OAC meeting when it involves the owner or designer, and record what actually happened in your daily report. If a missed handoff becomes a delay, that record supports a timely delay notice.

FAQ

What is pull planning in construction?

Pull planning is a team scheduling method where the GC and trade foremen start at a milestone and work backward, with each trade stating what it needs from the previous trade to start on time.

Is pull planning the same as the Last Planner System?

No. Pull planning is one part of the Last Planner System. The system also includes milestone planning, make-ready planning, weekly work planning, daily huddles, percent plan complete and reasons for variance.

How long should a pull planning session take?

For one phase of work, plan on roughly one to two hours. Larger phases or jobs with many trades may need to be split into separate sessions by area or phase.

What is percent plan complete (PPC)?

PPC is the number of weekly planned tasks completed as promised divided by the total number of tasks planned for that week. Teams track it alongside the reasons tasks were missed.

Who should attend a pull planning meeting?

The superintendent, the GC project manager and the trade foremen or field leads who can commit crews, plus suppliers or designers when long-lead items or open design questions affect the phase.

Keep pull plan commitments from getting lost

The hard part of pull planning is the follow-through: constraints, promises and handoffs scattered across texts, emails and meeting notes. CooperBuild AI keeps project chat, tasks and job records together, and its assistants can pick up action items from the team's conversation so the super and PM can see who owes what before the week starts. It also includes accounting with GL, AP and AR and connects to QuickBooks Online, so field and office work from the same project.

Get started with a free trial of CooperBuild AI and run your next look-ahead and weekly plan in one place.

Written by

Adam Hicks, CooperBuild AI