Change Order Markup: How Much Overhead and Profit Can GCs Charge?

Change order markup is the overhead and profit added to changed work. Typical caps, how to calculate it, sub markup rules and how GCs protect margin.

Published
Reading time
6 min read
Author
Adam Hicks
On this page8 sections
  1. What is a typical change order markup?
  2. Where does the contract set change order markup?
  3. How do you calculate change order markup?
  4. Can a GC mark up a subcontractor's change order?
  5. What does the markup have to cover?
  6. How can GCs protect their margin on changes?
  7. FAQ
  8. What is a normal markup on a change order?
  9. Is change order markup applied to cost or to cost plus overhead?
  10. Can a general contractor mark up a subcontractor's change order?
  11. Do you add overhead and profit on credit change orders?
  12. Price changes from the same record as the job

By Adam Hicks, CooperBuild AI · November 20, 2026

Change order markup is the overhead and profit a contractor adds to the direct cost of changed work. On most commercial and public jobs the contract sets it, often as separate caps for work you self-perform and for work your subs perform. When the contract is silent, the rate is a negotiation, and many GCs start from the markup they bid the job at.

That gap between "what the contract allows" and "what the change actually costs you" is where GCs lose money. As one commenter in an r/GeneralContractor thread on change order markup put it, "In commercial your contract terms dictate your overhead and profit for the contract and change orders" (r/GeneralContractor (opens in a new tab)). This guide covers how to find your allowed markup, how to calculate it correctly, and how to price changes so the markup is actually profit.

What is a typical change order markup?

There is no single industry number. It depends on the contract, the owner and who performs the work. A few published examples show the range:

  • U.S. Department of Veterans Affairs. For changes of $500,000 or less, the VA's clause caps overhead and profit at 10% each on the first $20,000, 7.5% each on the next $30,000, and 5% each on the balance over $50,000 (48 CFR 852.243-70 (opens in a new tab)).
  • U.S. General Services Administration. GSA negotiates overhead, and caps profit at 10% "unless entitlement to a higher rate of profit may be demonstrated." On work by subs within two tiers, the upper-tier firm gets 50% of its negotiated rates, no more than 10% combined (GSAR 552.243-71 (opens in a new tab)).
  • British Columbia (Canada). The BC Construction Association's supplementary condition allows up to 20% combined overhead and profit on self-performed work and up to 10% on subcontracted work (BCCA (opens in a new tab)).

On private work, practice varies widely. In the same Reddit thread, one contractor said their change orders range from 10-15% up to 100% for disruptive changes, while a GC in another thread said they limit subs to 15% on all change orders (r/GeneralContractor (opens in a new tab)). Treat these as anecdotes, not benchmarks. Your contract and your own overhead are the only numbers that matter.

Where does the contract set change order markup?

Look in three places before you price your first change:

  1. The changes clause in the general conditions. This defines what counts as cost and often caps overhead and profit.
  2. Supplementary or special conditions. Owners frequently override the base form here, for example with a lower cap or a declining scale.
  3. The subcontract. Your subcontracts should flow down markup limits that match or fit inside what the owner allows you. If the owner caps you at a total figure that includes sub markup, an uncapped subcontract means you eat the difference.

If none of these says anything, the markup is open to negotiation. Agree on rates in writing early, ideally in the contract, not on the first disputed change.

How do you calculate change order markup?

Order matters. Many contracts apply profit on top of cost plus overhead, which compounds. Under the VA clause, profit "shall be computed by multiplying the profit percentage by the sum of the direct costs and computed overhead costs." That means 10% overhead and 10% profit comes to 21% of direct cost, not 20%.

A simple example on $10,000 of self-performed direct cost:

  • Overhead at 10%: $1,000
  • Profit at 10% of $11,000: $1,100
  • Total change: $12,100

If the contract instead says "15% combined overhead and profit on cost," the total is $11,500. Read the formula, not just the percentages. Bond and insurance are often added last on the full value. GSA's clause, for example, applies bond and insurance after overhead and profit when those premiums are a percentage of the change value.

Also check how credits work. The VA clause requires credit items to be deducted before overhead and profit are added, so you mark up only the net increase. For more on why markup and margin percentages differ, see markup vs margin in construction.

Can a GC mark up a subcontractor's change order?

Usually yes, but at a lower rate and within limits. The common pattern is a full rate on your own work and a smaller fee on sub work, because the sub's price already includes the sub's overhead and profit. GSA's clause is explicit: no markup on a subcontractor's overhead or profit, and a reduced rate on sub direct costs.

Commenters in an r/ConstructionManagers thread on sub change orders split on the question. One said "If it flows through your books you mark it up," pointing to accounting work and liability, while another noted GCs typically "can't charge more than the O&P percentage on your sub's work" under the contract (r/ConstructionManagers (opens in a new tab)). Both can be true. The contract decides.

What does the markup have to cover?

More than most people assume. The VA clause states that overhead and fee include field and office supervision, small tools, incidental job burdens and home office expense, and that "review and coordination, estimating and expediting relative to contract changes" are included in overhead and fee. In other words, the hours your PM spends pricing a change may not be separately billable.

That's why a low capped markup can lose money on small, fiddly changes. The BCCA makes the same point: specified mark-ups sometimes "do not even cover the cost of putting together change order pricing," and pricing work for changes that don't proceed isn't paid at all.

How can GCs protect their margin on changes?

  • Price direct costs fully. If the markup is capped, put the real cost in the cost lines: supervision time that is direct to the change where the contract allows it, equipment, cleanup, protection, permits and extended general conditions if the schedule moves.
  • Ask for time, not just money. Record schedule days on every change, including zero. If a change extends the job, time-related costs may be recoverable separately depending on the contract (GSA's clause has a specific mechanism).
  • Negotiate the markup before signing. A declining scale or low cap is easier to change at bid time than after award.
  • Flow limits down to subs. Make sure your subcontract markup terms fit inside your owner contract.
  • Track every change from first notice. Use a change order log so you can see pending exposure, and follow a consistent change order process so nothing proceeds on a verbal go-ahead.
  • Use T&M where scope is unclear. When you can't price a change up front, time and material tickets signed daily protect the actual cost.

FAQ

What is a normal markup on a change order?

It depends on the contract. Public contracts often cap overhead and profit around 10% each on self-performed work, with lower caps on larger changes or on subcontracted work. On private work without a cap, many GCs start from the markup they bid the job at.

Is change order markup applied to cost or to cost plus overhead?

Read the contract formula. Many clauses, including the VA's, apply profit to direct cost plus overhead, so 10% overhead and 10% profit equals 21% of direct cost.

Can a general contractor mark up a subcontractor's change order?

Usually, but at a reduced rate. Many contracts allow a smaller fee on sub work and prohibit marking up the sub's own overhead and profit.

Do you add overhead and profit on credit change orders?

It depends on the contract. The VA clause has credits deducted before markup on mixed changes and allows a negotiated overhead and profit allowance in the credit for deleted-only work. Check your changes clause.

Price changes from the same record as the job

Change order markup is easier to get right when the change starts from your original estimate instead of a blank spreadsheet. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate is cloned into the live project, and vendor quotes, pay apps, payroll and the general ledger hang off the same deliverables. It includes built-in accounting (GL, AP and AR), connects to QuickBooks Online if you keep your books there, and takes payments through Stripe.

Start a free trial of CooperBuild AI and price your next change from the estimate you won the job with.