T&M Rate Sheet: How GCs Set Change Order Rates Before Work Starts

A T&M rate sheet sets labor, equipment and markup rates for change work before it starts. What GCs should include, review and attach to subcontracts.

Published
Reading time
6 min read
Author
Adam Hicks
On this page9 sections
  1. What is a T&M rate sheet?
  2. Why should GCs set T&M rates before work starts?
  3. What should a T&M rate sheet include?
  4. How do you build the labor rate?
  5. How should equipment be priced on a rate sheet?
  6. How do GCs review a subcontractor's rate sheet?
  7. How does a rate sheet turn T&M tickets into a change order?
  8. FAQ
  9. What is a T&M rate sheet?
  10. Does a T&M labor rate include overhead and profit?
  11. Should overtime be listed separately on a rate sheet?
  12. When should a GC get a sub's T&M rate sheet?
  13. Price the change the day it happens

By Adam Hicks, CooperBuild AI · November 26, 2026

A T&M rate sheet is a signed list of the hourly labor rates, equipment rates and markups that will price time-and-material change work on a job. GCs collect one from every sub and agree their own with the owner before work starts, usually as an exhibit to the contract. When a change has to go T&M, nobody argues about the rate later, only the hours.

This guide covers what goes on a T&M rate sheet, how to review a sub's rates, and how the sheet turns signed tickets into change orders.

What is a T&M rate sheet?

It is the price list for work you can't price in advance. The T&M ticket records the hours, equipment and material used on a change. The rate sheet says what each of those hours costs.

Without one, every ticket becomes two negotiations: did the crew really spend those hours, and what is an hour worth? With one, only the first question is left.

On federal time-and-materials contracts the idea is written into the rules. FAR 52.232-7 says the hourly rates in the contract "shall include wages, indirect costs, general and administrative expense, and profit," and are multiplied by the direct labor hours worked (Acquisition.gov (opens in a new tab)). Private and state work isn't bound by that clause, but the principle is the same: the rate is set first, the hours are counted later.

Why should GCs set T&M rates before work starts?

Because the cheapest time to agree on a rate is before anyone needs it. Stoel Rives notes that "sophisticated parties attempt to set change order pricing ahead of time in the underlying contracts," stipulating unit prices, equipment rates and profit percentages in advance to prevent arguments later (Stoel Rives (opens in a new tab)).

It also shows up in day-to-day practice. An electrical subcontractor on r/ConstructionManagers (opens in a new tab) wrote that "whenever we sign a contract, we're asked our CO rates," and that he keeps an updated rate sheet to answer. A GC in the same thread said that from a union sub with published rate sheets, he would expect the published rate plus an overhead and profit markup.

For the GC, the payoff is speed. When the owner directs extra work in the field, you can start on T&M the same day, knowing the price formula is already agreed on both sides.

What should a T&M rate sheet include?

Keep it to one or two pages, and make every line something a project manager can check against a ticket.

  • Labor classifications. Foreman, journeyman, apprentice and laborer, each with its own rate. Avoid a single blended rate unless the contract allows it.
  • Straight time, overtime and premium time. List each separately. FAR 52.232-7, for example, doesn't vary the hourly rate for overtime unless the schedule says so, which is why the rate sheet should spell it out.
  • What the labor rate includes. Wage, fringes, payroll taxes, workers' comp and liability insurance, and whether overhead and profit are already in the rate or added as a markup.
  • Equipment rates. Owned equipment by the hour or day, with the rate source (internal rate, a published rate book or a public agency schedule). Rented equipment at invoice cost plus the agreed markup.
  • Materials. Billed at invoice cost plus a stated markup, with receipts.
  • Small tools and consumables. Either built into the labor rate or a stated percentage, never both.
  • Lower-tier subs. Their invoice plus a stated markup.
  • Non-billable roles. Say whether PM, estimator and superintendent time can be billed, or is covered by the markup.
  • Effective dates. When the rates expire, and how escalation (for example, a new union agreement) is handled.

How do you build the labor rate?

Start from what an hour actually costs you, then add what the contract allows.

The cost side is wage plus labor burden: payroll taxes, workers' comp, insurance, benefits and paid time off. Public agencies treat that burden as a separate line. Caltrans, for example, pays force account labor at actual wages plus a published labor surcharge that covers workers' comp, social security, Medicare, federal and state unemployment and state training taxes; its September 2026 rate book sets the general surcharge at 10 percent for regular time and overtime, with higher rates for certain trades (Caltrans (opens in a new tab)).

Then add overhead and profit, either inside the rate or as a markup on top. The contract decides which, and how much. Our guide to change order markup covers how those caps usually work.

How should equipment be priced on a rate sheet?

Owned equipment should bill at a rate that covers ownership and operating cost, not just fuel. Our post on equipment cost per hour walks through the math.

Public rate books are a useful cross-check. The Caltrans rate book explains that its rates cover fuel, oil, repairs, depreciation, storage and other ownership costs but not the operator, and that its calculated rates are "likely to be lower than the rate charged by a rental yard" (Caltrans rate book (opens in a new tab)). It also uses reduced rates for overtime and ownership-only rates for delays, so a rate sheet that bills full equipment rates for idle time deserves a question.

How do GCs review a subcontractor's rate sheet?

Ask for the sheet with the bid, and review it during buyout, not after the first ticket.

  1. Check each classification against the crew you'll actually see. A sheet full of foreman rates on a crew of apprentices is a red flag.
  2. Ask what's in the rate. If overhead and profit are already in the hourly rate, the sub shouldn't add a second markup on the ticket.
  3. Compare against your other bidders. If one sub's rates are well above the others, ask why before the subcontract is signed.
  4. Confirm the markup ties to your prime contract. If the owner caps your markup on sub work, a sub rate sheet that exceeds the owner's rules leaves you paying the difference.
  5. Attach it to the subcontract. A rate sheet in an email thread is a starting point. A rate sheet in the subcontract exhibits is the deal.

How does a rate sheet turn T&M tickets into a change order?

Each signed ticket lists hours by classification, equipment hours and materials. Multiply by the rate sheet, add the agreed markups, and you have a priced change request with backup the owner has already seen.

Roll those priced tickets into the change order log daily, not at month-end. Tickets that sit unpriced for weeks are where scope fights and missed billings start.

This article is general information, not legal advice. Change pricing rules depend on your contract and state law, so check your prime contract and subcontracts with a construction attorney.

FAQ

What is a T&M rate sheet?

A T&M rate sheet is a signed list of hourly labor rates, equipment rates and markups used to price time-and-material change work. It is usually agreed before work starts and attached to the contract or subcontract.

Does a T&M labor rate include overhead and profit?

It can. Some rate sheets build overhead and profit into the hourly rate, while others bill a cost rate and add a markup. The sheet should say which, so the markup isn't charged twice.

Should overtime be listed separately on a rate sheet?

Yes. List straight time, overtime and premium time rates separately, and state when overtime can be billed, such as only with prior written approval.

When should a GC get a sub's T&M rate sheet?

With the bid or during buyout, before the subcontract is signed. That way the rates can be compared across bidders and attached as an exhibit.

Price the change the day it happens

A rate sheet only helps if someone applies it to the ticket while the work is fresh. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate becomes the live project, and subcontracts, change orders, pay apps, payments and the general ledger hang off the same deliverables. It has built-in accounting (GL, AP and AR), connects to QuickBooks Online, and takes payments through Stripe. Stop stacking Procore, QuickBooks and a spreadsheet to price T&M work after the fact.

If you want your change pricing and job cost on one record, start a 14-day free trial (opens in a new tab).