- What is concurrent delay in construction?
- Do you get a time extension for concurrent delay?
- Can a contractor recover delay costs during concurrent delay?
- What is pacing delay?
- How do you prove concurrent delay?
- Keep the delay record while the job is running
By Adam Hicks, CooperBuild AI · November 17, 2026
Concurrent delay in construction happens when an owner-caused delay and a contractor-caused delay overlap and each one, on its own, would have pushed out the completion date. Unless the contract says otherwise, the usual result in U.S. practice is "time but no money": the GC gets a time extension, so the owner cannot collect delay or liquidated damages for that period, but the GC cannot recover its extended overhead either.
That rule sounds simple. In practice it decides who eats weeks of general conditions, so it is worth knowing how owners raise it, how it is measured and what records protect you. This guide covers the definition, the common outcomes, pacing, and the documentation habits that keep a concurrency defense from swallowing a good claim.
What is concurrent delay in construction?
Concurrent delay is two or more delays, at different parties' risk, that hit the critical path in the same period. Long International (opens in a new tab) describes it as an owner-caused delay and a contractor-caused delay on the same activity, or on parallel paths that are equally critical, where each would have delayed completion by itself.
New Zealand law firm Russell McVeagh (opens in a new tab) gives two clear examples. A contractor claims weather delay, but it was short of labor that day and could not have worked anyway. Or a contractor claims delay from owner-provided structure defects, but its own roofing was already late and had to finish before the affected work could start.
Both delays must actually be critical. If one of them sits on a path with float, it is coincidental delay, not concurrent delay, and only the critical one controls the completion date.
How does concurrent delay come up on a job?
It usually shows up as a defense. You send a construction delay notice and a request for time and money, and the owner answers that you were late on something else during the same window.
A typical example is the r/ConstructionManagers thread "Concurrent Delay" (opens in a new tab). A PM asked whether a contractor already running four months behind its own schedule still earns a month when the owner causes a one-month delay. The top answers said yes, but only as a 30-day non-compensable extension: the owner's month comes off the late finish, and the contractor still owns the other three months.
Some commenters disagreed on whether that was really concurrency at all. That disagreement is normal. Whether delays are truly concurrent depends on the schedule facts and the contract wording.
Who pays when delays are concurrent?
Read your contract first. Long International notes that many contracts are silent on concurrency, some state that neither party recovers delay costs during concurrent periods, and a few go further and deny the time extension too. That last version puts real liquidated damages risk on the GC and deserves a lawyer's review before you sign.
When the contract is silent, Long International describes three U.S. approaches:
- Time but no money. The contractor gets an extension, so the owner cannot collect liquidated damages for the period, but the contractor gets no extended overhead.
- Apportionment. Courts split delay damages when the evidence lets them separate the days each party caused.
- Critical path analysis. A schedule analysis assigns responsibility for each delay day based on what actually drove completion.
The key federal case is Blinderman Construction Co. v. United States, 695 F.2d 552 (Fed. Cir. 1982) (opens in a new tab). As summarized in a Lexology article on apportionment (opens in a new tab), the party seeking recovery must separate its delays from the other side's. If it cannot, the delays are treated as "concurrent or intertwined," and neither party recovers.
The same article adds that courts mostly apportion time, not fault percentages. They decide which days belong to which party, rather than calling a problem 60% owner and 40% contractor.
How is concurrent delay measured?
With the schedule, window by window. A time impact analysis or a forensic schedule analysis looks at each update period, identifies what drove the critical path and shows which delays overlapped.
Float matters. Long International walks through an AACE International example: the owner delays one activity 5 days and the contractor delays a parallel activity 3 days, but the two paths differ by 2 days of float. The result is a 5-day extension, 3 days of non-compensable concurrent delay and 2 days of compensable owner delay.
The same article notes that the Society of Construction Law's Delay and Disruption Protocol reaches a similar result to AACE. The contractor gets the time for the owner's delay but no delay costs for the concurrent period.
What is the difference between pacing and concurrent delay?
Pacing is a deliberate choice. Long International defines pacing delay as a contractor's conscious, contemporaneous decision to slow independent work because another activity was already delayed. Concurrent delay is involuntary: the second activity was slowed by its own problems.
The difference is worth money. If the owner's late equipment delivery creates float and you sensibly slow piping elsewhere to save cost, that should not be treated as your own delay. The catch is proof. A pacing decision you cannot show in writing from the time it was made looks a lot like a delay you caused.
How can GCs protect themselves from a concurrent delay defense?
Most of this is record keeping, done while the job is running:
- Update the schedule monthly and keep every version. Window analysis only works if the updates exist and match what happened.
- Give notice for every owner delay, on time. Late notice hands the owner a second defense on top of concurrency.
- Log your own problems honestly. Daily reports that note crew size, weather and sub no-shows let you show your delays were off the critical path, or were paced.
- Write down pacing decisions. A dated email or meeting minute saying "slowing interior framing while we wait on the owner's steel revision" is the evidence pacing needs.
- Track extended general conditions by day. If you cannot separate the cost of the owner's days, Blinderman says you may recover nothing.
- Read the concurrency language before you bid. Pair it with the liquidated damages clause to see what a late finish actually costs you.
This is general information, not legal advice. Concurrency rules vary by contract and jurisdiction, so bring in counsel or a scheduling consultant on a real claim.
FAQ
What is concurrent delay in construction?
Concurrent delay is when an owner-caused delay and a contractor-caused delay overlap in the same period and each would have delayed project completion on its own.
Do you get a time extension for concurrent delay?
Often yes. When the contract is silent, the common U.S. outcome is a time extension with no delay damages, so the owner cannot collect liquidated damages for that period either.
Can a contractor recover delay costs during concurrent delay?
Usually not for the concurrent period. A contractor can recover costs only for delay days it can clearly separate and prove were caused by the owner.
What is pacing delay?
Pacing delay is when a contractor deliberately slows independent work because another activity was already delayed by the owner. It is treated differently from concurrent delay if it is documented when it happens.
How do you prove concurrent delay?
With schedule analysis, usually a window-by-window review of monthly updates, backed by daily reports, notices and cost records that show which delays drove the critical path.
Keep the delay record while the job is running
Concurrency fights are won or lost on records nobody enjoys keeping: schedule updates, daily reports, notices and day-by-day overhead. CooperBuild AI keeps project chat, tasks and job costs in one place, and its assistants can pick up action items, like "send delay notice for the steel revision," from the team's conversation so they are not forgotten. It includes built-in accounting with GL, AP and AR, connects to QuickBooks Online and supports integrated payments through Stripe.