Time Impact Analysis: How GCs Prove a Time Extension

A time impact analysis shows how many days a delay added to your schedule. How GCs build one step by step, what goes in it, and why TIAs get rejected.

Published
Reading time
6 min read
Author
Adam Hicks
On this page10 sections
  1. What is a time impact analysis in construction?
  2. When do GCs need a time impact analysis?
  3. How do you prepare a time impact analysis step by step?
  4. What is a fragnet?
  5. Why does the critical path matter in a TIA?
  6. What should a TIA write-up include?
  7. Why do time impact analyses get rejected?
  8. Does a TIA get you paid for the delay, too?
  9. How CooperBuild AI helps
  10. FAQ
  11. What is the difference between a delay notice and a time impact analysis?
  12. Which schedule should I use for a time impact analysis?
  13. Do I need scheduling software to do a time impact analysis?
  14. Does a time impact analysis prove I'm owed money?

By Adam Hicks, CooperBuild AI · November 12, 2026

A time impact analysis (TIA) is a forward-looking schedule check that shows how much a specific delay event pushes your completion date. You take the last accepted schedule update from before the event, insert a small set of activities that models the delay (a "fragnet"), recalculate, and compare the finish date before and after. The difference is the time you ask for.

Sending a construction delay notice keeps your rights alive. The time impact analysis is what proves how many days you're owed. This guide walks through how GCs build one, what reviewers look for, and the mistakes that get TIAs rejected.

What is a time impact analysis in construction?

It's a method for measuring the schedule effect of one delay event, or a group of related events, while the job is still going. It's called prospective because you're forecasting the impact, not reconstructing it after the fact.

AACE International publishes a recommended practice for it, RP 52R-06, "Time Impact Analysis – As Applied in Construction." Many specs and owner reps point to it, and it's worth reading if you do a lot of public or institutional work.

A TIA answers one question: if this event hadn't happened, when would we finish, and when will we finish now that it has?

When do GCs need a time impact analysis?

Any time you're asking for a time extension and the contract or the owner wants support for the number of days. Common triggers:

  • An owner-directed change that adds work on or near the critical path
  • A late RFI answer or design revision that holds up a key activity
  • Differing site conditions
  • A suspension or stop-work order
  • Late owner-furnished equipment, access or permits

Read the scheduling and change clauses in your contract. Some specs require a TIA with every time extension request and spell out the format. On federal work, FAR 52.236-15 (Schedules for Construction Contracts) requires the contractor to submit a practicable progress schedule and record actual progress on it as the contracting officer directs, and many agencies add more detailed scheduling specs on top of that. If you don't have a working CPM schedule that's updated and accepted, a TIA gets much harder to defend.

How do you prepare a time impact analysis step by step?

Here's the basic flow most schedulers follow.

  1. Pin down the event. What happened, when it started, and the documents that prove it: the directive, the RFI and its response date, the letter, the photos, the daily reports.
  2. Pick the right schedule update. Use the last accepted update with a data date before the event started. Don't use the original baseline unless it's the only schedule you have. The baseline doesn't reflect what's already slipped, so you'd mix this event's impact with everything else.
  3. Check that update is clean. Progress current, no open ends, and no date constraints holding the finish in place. A constraint on the completion milestone will hide any impact you insert.
  4. Build the fragnet. Add only the activities the event created, like "redesign footing at grid C-4" or "wait for revised drawings." Give each one a duration you can back up.
  5. Tie it in. Link the fragnet to the existing activities it really affects, and nothing more.
  6. Recalculate. Let the scheduling software compute the new dates. Don't type finish dates by hand.
  7. Compare. Measure the change in the forecast completion date and any contract milestones. That's the impact.
  8. Write it up and submit it with the native schedule files.

What is a fragnet?

A fragnet is a fragment of a network: a short chain of new activities and logic that represents the delay event. If an owner change adds a conduit run under a slab, your fragnet might be "receive change directive," "revise layout," "install added conduit" and "inspect," tied ahead of the slab pour.

Reviewers rarely argue with the math. They argue with the fragnet. Where did that 14-day duration come from? Is the new work really a predecessor of the whole slab, or just one pour? A duration backed by a letter, a quote or a sub's written schedule holds up much better than an estimate with no basis.

Why does the critical path matter in a TIA?

You generally earn time only when the event delays the critical path, the longest chain of work driving completion. If the event eats float on a non-critical activity and the finish date doesn't move, the TIA usually shows no time owed.

That's why the schedule update matters so much. If your schedule doesn't show the real critical path, the analysis won't either. Keeping a clean 3-week look-ahead schedule tied to the master schedule helps you spot critical-path hits early, before you're writing the request.

What should a TIA write-up include?

Keep it short enough that a reviewer can rebuild your result from it:

  • The event, its start date and the source documents
  • The schedule update you used, its data date, and why you picked it
  • A table of fragnet activities with durations, logic ties and the basis for each duration
  • Forecast completion and milestone dates before and after
  • One or two sentences on the critical path before and after
  • Any mitigation you looked at, like re-sequencing or added crews, and why it was or wasn't modeled
  • Both native schedule files

Attach the backup. Daily reports, RFI logs and photos written the day things happened carry more weight than anything assembled months later. Our guide to the construction daily report covers what to capture.

Why do time impact analyses get rejected?

The same problems come up again and again:

  • Wrong schedule basis. Using the baseline or an update from long before the event.
  • Stale progress. Activities that are actually done are still driving the dates.
  • Hidden constraints. A finish constraint means nothing moves no matter what you insert.
  • Padded durations. Fragnet activities with built-in float or no backup.
  • Mixed causes. Contractor-caused delay folded in with owner-caused delay.
  • Double counting. Analyzing overlapping events separately against the same update and adding the results. Insert overlapping events together, or one after another in date order.
  • No notice. A strong TIA can still fail if the delay notice was late or never sent.

Does a TIA get you paid for the delay, too?

Not by itself. A TIA supports time. If the delay is compensable under your contract, you still need to price it: extended general conditions, idle equipment, re-sequencing and escalation. Track those costs to their own cost codes from the day the delay starts, so the dollars line up with the days in your TIA. If you're facing an LD assessment, an approved extension is often your best defense. See our guide to liquidated damages in construction.

How CooperBuild AI helps

A TIA is only as good as the records behind it. CooperBuild AI keeps job chat, daily reports, RFIs, schedules and change orders in one place, with full accounting built in. Assistants pull action items like "send delay notice" out of job conversations so they don't get lost, and can draft daily reports from project chat for your team to review. When it's time to price the delay, your job costs are already tracked in the same system.

If you want to see it on your own jobs, start a free trial.

FAQ

What is the difference between a delay notice and a time impact analysis?

A delay notice tells the other party a delay happened and reserves your rights. A time impact analysis comes after and shows how many days the event added to the schedule, using the last accepted update and a fragnet.

Which schedule should I use for a time impact analysis?

Use the last accepted schedule update with a data date before the delay event started. The original baseline usually isn't the right basis because it doesn't reflect delays that already happened.

Do I need scheduling software to do a time impact analysis?

In practice, yes. A TIA depends on a logic-driven CPM schedule that recalculates dates when you insert the fragnet. Hand-adjusted dates or a bar chart without logic are hard to defend.

Does a time impact analysis prove I'm owed money?

No. A TIA supports a time extension. Whether you also recover costs depends on the contract and the cause of the delay, and you'll need to price those costs separately.