Notice to Cure in Construction: How GCs Handle a Defaulting Sub

A notice to cure in construction gives a defaulting sub a written chance to fix it. What to include, how to deliver it, and what comes next.

Published
Reading time
6 min read
Author
Adam HicksFounder, CooperBuild AI
On this page9 sections
  1. What is a notice to cure in construction?
  2. When should a GC send a notice to cure?
  3. What should a notice to cure include?
  4. How do you deliver it?
  5. What happens if the sub doesn't cure?
  6. What if the default turns out to be wrongful?
  7. How do you avoid getting to a notice to cure?
  8. Where CooperBuild AI fits
  9. FAQ
  10. What is a notice to cure in construction?
  11. How long does a subcontractor have to cure a default?
  12. Can a notice to cure be sent by email?
  13. Do I have to notify the surety?

By Adam Hicks, CooperBuild AI · November 21, 2026

A notice to cure in construction is a written letter from the general contractor telling a subcontractor exactly how it is in default, what it must do to fix it, and by when, before the GC can supplement the work, withhold payment, or terminate. Most subcontracts make the notice a condition of those remedies, so a sloppy or skipped notice can turn the GC into the party in breach. Send it early, make it specific, and follow the exact steps your subcontract spells out.

This article is general information, not legal advice. Read your own subcontract and talk to a construction attorney before declaring a default.

What is a notice to cure in construction?

A notice to cure (also called a cure notice or default notice) is the formal step between "we keep emailing them" and "we are bringing in someone else." It does three jobs:

  • It names the specific default, tied to the subcontract language.
  • It gives the sub a defined window to start, and keep up, a cure.
  • It preserves the GC's right to use the subcontract's remedies if the cure doesn't happen.

A Texas Contractor article by construction attorneys at Chapman Negrete puts the risk plainly: failing to follow a notice-to-cure provision "may transform the non-breaching contractor into the party guilty of committing a material breach," and terminating without giving the required chance to cure can expose the GC to a wrongful termination claim.

When should a GC send a notice to cure?

Send it when the problem is real, it belongs to the sub, and talking hasn't fixed it. Common triggers:

  • Persistent failure to keep up with the schedule (manpower short of what the look-ahead needs, missed milestones).
  • Not paying their own suppliers or sub-subs, which puts lien and stop-notice exposure back on the job.
  • Defective or non-conforming work that isn't being corrected.
  • Missing deliverables such as submittals, insurance certificates, or safety plans that hold up other trades.

ConsensusDocs 750, a widely used standard subcontract, lists persistent failure to maintain progress, failure to pay subs and suppliers, and failure to follow laws and orders of public authority, plus a catch-all for any other material breach. Your subcontract may use different wording; the notice should track whatever yours says.

Before you send anything, check that the delay is actually theirs. In an r/Construction thread on putting a sub on notice, one subcontractor warned that GC notices sent without that homework "never turned out well for the GC." If the sub is waiting on your RFI answer, a late change order, or another trade, fix that first. A construction delay notice record from your own side helps you tell the difference.

What should a notice to cure include?

Keep it factual and specific. A strong notice includes:

  1. The subcontract clause you are invoking. Say plainly that this is a notice to cure under that section.
  2. Every default, not just the worst one. List dates, locations, and what the subcontract or schedule required. Add a line that the list is not exhaustive and that leaving something out doesn't waive it.
  3. The cure you expect. Be concrete: "Staff the level 2 framing with a minimum of six carpenters starting Monday and recover the north wing to the current look-ahead by the 15th." If your clause requires the sub to commence a cure within a set number of days, ask only for actions that can actually start in that time.
  4. The deadline, matching the subcontract's cure period.
  5. The consequences the subcontract allows if the cure fails: supplementing the work, withholding payment for the cost, or termination.
  6. A reservation of rights, so the notice doesn't read as accepting the late or defective work.

Attach the backup: daily reports, photos, the look-ahead, and the email trail. That record is what you will lean on if the dispute escalates.

How do you deliver it?

Follow the notice clause in the subcontract to the letter: the address, the person, and the method it requires. In a ConsensusDocs newsletter on CD 750 Article 10, attorney Charles Surasky advises against relying on email, because the notice can get lost in a flood of job email. He recommends a letter hand delivered to the sub's designated representative, with a copy sent by overnight delivery to the sub's home office.

If the sub is bonded, read the performance bond. Under CD 750, the first notice goes to the sub; if the sub hasn't started a satisfactory cure within three business days, a second notice goes to the sub and its surety, at the notice address in the bond, and the sub gets two more business days. Other subcontracts and bond forms set different steps, but many sureties have conditions on notice before they have to perform. Missing them can cost you the bond you paid for.

What happens if the sub doesn't cure?

Termination is only one option, and usually not the first. Depending on your subcontract, remedies can include:

  • Supplementing the sub's work with your own forces or another subcontractor, and charging the cost back.
  • Withholding payment due the sub to cover those costs.
  • Terminating for default, which on a bonded sub may trigger the surety's obligation to complete the work.

Surasky's article recommends sending the defaulted sub frequent, detailed accountings of the costs incurred on its behalf, because clean cost records help avoid litigation and lower its cost if it comes. That is the same discipline as a well-run construction backcharge: every hour, invoice, and markup tied to the sub's scope and documented as it happens.

What if the default turns out to be wrongful?

The downside of moving too fast is real. On federal fixed-price construction work, FAR 52.249-10 says that if a contractor's right to proceed is terminated and it is later found that the contractor was not in default or the delay was excusable, the termination is treated as if it were for the convenience of the government. Many private subcontracts copy that idea. A wrongful default termination can leave the GC paying the sub's costs and profit while also paying the replacement sub.

That is why the notice, the cure period, and the backup matter more than the tone of the letter.

How do you avoid getting to a notice to cure?

The best cure notice is the one you never send. A few habits help:

  • Put the dates in the subcontract. Submittal deadlines, manpower commitments, and milestone dates the sub signed up for are far easier to enforce than dates set in a weekly meeting.
  • Track commitments in writing every week. Action items from the OAC and sub meetings, with an owner and a date, build the record before you need it.
  • Watch the money. Compare the sub's pay apps to actual progress during your subcontractor pay application review so overbilling doesn't leave you short when you need to supplement.
  • Have a backup sub in mind on critical-path scopes.

Where CooperBuild AI fits

Notices to cure go wrong when the facts are scattered: the schedule in one tool, daily reports in another, the sub's commitment and pay apps in accounting, and the promises in a group text. CooperBuild AI keeps the estimate, the schedule, subcontract commitments, pay apps, and job costs in one system, with built-in accounting (GL, AP, AR) and a QuickBooks Online connection. When a sub falls behind, the dates, the dollars, and the action items are already in one place, and assistants help you pull them together into a draft you review before anything goes out.

If you want to see it on a real job, start a free trial or book a 20-minute working session on your last bid at cooperbuild.ai.

FAQ

What is a notice to cure in construction?

It is a written notice from the GC to a subcontractor that identifies a specific default under the subcontract, states what the sub must do to fix it, and sets a deadline, before the GC can use remedies such as supplementing the work, withholding payment, or terminating.

How long does a subcontractor have to cure a default?

It depends on the subcontract. Some give a few days to start a cure; ConsensusDocs 750 uses three business days after the first notice and two more after a second notice to the sub and its surety. Use the exact period in your contract.

Can a notice to cure be sent by email?

Only if the subcontract's notice clause allows it, and even then many construction attorneys recommend a hand-delivered or overnight letter so the notice is not lost in routine job email. Follow the notice clause to the letter.

Do I have to notify the surety?

If the sub has a performance bond, read the bond and the subcontract. Many bonds require notice to the surety before a default can be declared, and missing that step can put your claim on the bond at risk.

Written by

Adam Hicks, Founder, CooperBuild AI