- What should a GC check on a subcontractor pay application?
- How do you catch overbilling on a sub pay app?
- Can a subcontractor bill for pending change orders?
- When should subcontractors submit pay applications?
- What happens if a sub pay app is wrong?
- Review sub billing where the job already lives
By Adam Hicks, CooperBuild AI · November 19, 2026
A subcontractor pay application review is the check a GC runs before approving a sub's monthly bill: paperwork first, then each schedule of values line against work in place, then retainage, stored materials, change orders and the math. Anything that fails goes back to the sub or gets approved at a reduced amount with the reason written down. Done before the cutoff, it keeps you from paying for work that isn't there.
Every sub you pay at full billed value is a loan you didn't agree to make if the work isn't in place. This guide is the monthly routine we'd want any project manager to run, in the order that ends a bad review fastest.
Why does the subcontractor pay app review matter?
Approval is the moment a sub's number becomes your job cost, your payable and, a few days later, your cash out the door. If accounting approves on arithmetic alone, the sub's billing becomes your progress record.
Front-loading is the usual reason the numbers drift. In one long r/Construction thread on monthly pay apps, a top commenter put it plainly: "Everybody front loads their schedule of values a bit" (r/Construction (opens in a new tab)). A bit is normal. Approving it without checking is how you end up holding the risk if the sub walks late in the job.
Your own billing depends on it too. When you bill the owner on the same schedule, an overbilled sub line flows straight into your pay application, and the owner's reviewer will find it.
When should subs submit their pay applications?
Before you need to bill the owner. If your pay application to the owner is due on the 25th, set the sub cutoff several days earlier so there is time to walk the work and roll approved amounts into your own billing.
Put that cutoff date in the subcontract, not in an email in month three. Many GCs also run a pencil draft: the sub sends a draft a few days ahead, the superintendent and PM mark it up against the field, and the final arrives already agreed. A pay app that misses the cutoff rolls to next month's cycle.
What paperwork should you check before the numbers?
Some pay apps can't be approved however good the numbers look. Check these first, because they're fast and they end the review early:
- Executed subcontract. No billing against an unsigned agreement.
- Current certificate of insurance that meets the subcontract's limits and endorsements, and won't lapse during the period.
- Lien waivers your contract requires, typically a conditional waiver for this payment and an unconditional one for the last payment you made. Our lien waiver guide covers the difference.
- Certified payroll on prevailing-wage work, current through the billing period. On federal Davis-Bacon jobs that's the weekly payroll the Department of Labor's optional Form WH-347 (opens in a new tab) is built for.
- Bonds, if the subcontract requires them before first payment.
- An authorized signature on the application itself.
How do you check each line against the schedule of values?
With the gate cleared, open the continuation sheet and compare it line by line to the subcontract's schedule of values:
- Structure matches. Same lines, same scheduled values, same order as the approved schedule. New lines only come in through executed change orders.
- Previous work ties out. The "from previous applications" column should equal what you approved last month, line by line. A mismatch means the sub is billing from a different baseline.
- This period matches the field. Percent complete should agree with what the superintendent sees, the daily reports and site photos.
- Nothing over 100%. No line exceeds its scheduled value, and total completed to date stays within the revised subcontract (original plus executed change orders).
- Front-loading flagged. Mobilization, general conditions or early phases billed well ahead of the work get questioned.
When the field and the pay app disagree, settle the number with the sub before approval. Approving the sub's figure "to keep things moving" and fixing it next month means paying for work that isn't in place.
How should a GC verify percent complete?
Have someone who has seen the work sign off, not someone comparing it to last month's invoice. The cleanest control is the superintendent or PM marking up each line before accounting touches it.
Walk the questionable lines instead of debating them by email. If drywall is billed at 90% and the north wing hasn't been hung, the line goes back. Photos and daily reports settle most arguments faster than a site meeting does.
How do you check retainage and stored materials?
Retainage. Withhold at the subcontract rate on each line's billed amount, including any reduction the subcontract allows after a set percent complete. Track it per line and per sub so releases and closeout are clean. Rules vary by state and by public versus private work, so confirm the rule for your project. Our retainage guide covers timing and caps.
Stored materials. Only approve materials billed but not installed if the subcontract allows it, and only with the support it requires: supplier invoices, proof of insurance and the storage location. See stored materials billing for what to ask for.
How do change orders and backcharges show up?
Only executed change orders get billed, each as its own line referencing the change order number. Pending, verbal or "approved in concept" changes aren't billable yet; route them through your change order process first.
Backcharges you've issued come off this application, with the backup attached. Don't let them sit until closeout, when the sub has the least reason to agree.
What should you do when a pay app fails review?
You have three outcomes, and each should be written down:
- Approve as billed when every check passes.
- Approve at a reduced amount, with the reason for each adjusted line.
- Return for revision when the paperwork gate fails or the changes are too large to note.
Log the reviewer, the date and the disposition. If the owner, surety or an auditor later asks how a payment was approved, that log is your answer. Then check the arithmetic one last time: work completed, stored materials, retainage, less previous payments and current payment due should all foot.
FAQ
What should a GC check on a subcontractor pay application?
Paperwork first (executed subcontract, insurance, required lien waivers, certified payroll where needed), then each schedule of values line against work in place, retainage, stored materials support, executed change orders, backcharges and the math.
How do you catch overbilling on a sub pay app?
Have the superintendent or PM confirm percent complete line by line against the field, daily reports and photos before accounting approves. Question any line that runs ahead of the work, especially early-phase lines.
Can a subcontractor bill for pending change orders?
Not as approved work. Only executed change orders belong on the pay application, each as its own line. Pending changes go through approval first.
When should subcontractors submit pay applications?
Several days before the GC's own pay application is due to the owner, on a cutoff date written into the subcontract, so the GC has time to review and roll the numbers up.
What happens if a sub pay app is wrong?
The GC approves it at a reduced amount with each adjustment noted, or returns it for revision. Either way, record who reviewed it, when, and why.
Review sub billing where the job already lives
Most of this review is matching one document against another: the sub's billing against the subcontract, the field and last month's approval. CooperBuild AI keeps the estimate, the live project, vendor quotes and pay apps on the same deliverables, with built-in accounting (GL, AP and AR), a QuickBooks Online connection if you keep your books there, and integrated payments through Stripe. Its assistants can pull follow-ups out of project chat, so a missing waiver or a disputed line doesn't get lost.
Start a free trial of CooperBuild AI and run your next pay app cycle from one place.