  1. What is a pay-when-paid clause?
  2. What is a pay-if-paid clause?
  3. Pay-when-paid vs pay-if-paid: the side-by-side
  4. Are pay-if-paid clauses enforceable?
  5. How do federal jobs handle pay-when-paid?
  6. What should a GC do with these clauses?
  7. What should a sub look for before signing?
  8. How to keep sub payments from stalling
  9. FAQ
  10. What is the difference between pay-when-paid and pay-if-paid?
  11. Is pay-if-paid legal in every state?
  12. How long can a GC wait under a pay-when-paid clause?
  13. Does a pay-if-paid clause stop a sub from filing a mechanic's lien?

By Adam Hicks, CooperBuild AI · November 13, 2026

Pay-when-paid vs pay-if-paid comes down to one question: who eats it if the owner never pays? A pay-when-paid clause only sets the timing, so the GC can wait a reasonable time for the owner's money but still owes the sub in the end. A pay-if-paid clause makes the owner's payment a condition of paying the sub at all, and several states won't enforce it.

If you're a GC writing subcontracts, or a sub reading one, those two clauses look almost identical on paper. One word changes who carries the owner's credit risk. Here's how they work, where they hold up, and how to run your payables so the clause rarely matters.

This is general information, not legal advice. Contingent payment law varies by state and changes, so have a construction attorney in your state review your subcontract language.

What is a pay-when-paid clause?

A pay-when-paid clause ties the sub's payment date to when the GC gets paid. Typical wording says the contractor will pay the subcontractor within so many days after the contractor receives payment from the owner for that work.

Most courts read this as a timing rule, not a waiver. The California Supreme Court summed up the majority view in Wm. R. Clarke Corp. v. Safeco Ins. Co. (1997): unless the language plainly says otherwise, "pay when paid" just fixes the usual time for payment, and the sub still has a right to be paid within a reasonable time. The Sixth Circuit said much the same back in Thos. J. Dyer Co. v. Bishop International Engineering Co. (1962).

So under pay-when-paid, if the owner is slow, the sub waits. If the owner never pays, the GC still owes the sub after a reasonable time.

What is a pay-if-paid clause?

A pay-if-paid clause makes the GC's receipt of payment a condition precedent to paying the sub. If the owner never pays, the GC may never owe the sub for that work. The owner's credit risk moves down the chain.

Courts don't like forfeitures, so a pay-if-paid clause usually has to be unmistakable. Words like "condition precedent," "only if," and an express statement that the sub accepts the risk of owner nonpayment are what make it a pay-if-paid clause. If the language is fuzzy, expect a court to read it as pay-when-paid.

Pay-when-paid vs pay-if-paid: the side-by-side

Pay-when-paid Pay-if-paid
What it controls Timing of payment Whether payment is owed at all
Owner pays late Sub waits a reasonable time Sub waits
Owner never pays GC still owes the sub GC may owe nothing (where enforceable)
Who carries owner credit risk GC Sub
Typical trigger words "within X days after receipt" "condition precedent," "only if"
Enforceability Widely enforced as a timing term Limited or void in some states

Are pay-if-paid clauses enforceable?

It depends on the state, and on whether the job is public or private. A few examples with sources:

  • New York: void as against public policy. In West-Fair Electric Contractors v. Aetna Casualty & Surety Co. (1995), the Court of Appeals held that a clause forcing the sub to take the risk of owner nonpayment violates Lien Law § 34. A clause that only fixes a time for payment is fine.
  • California: unenforceable. Clarke v. Safeco held pay-if-paid clauses are an indirect waiver of the sub's mechanic's lien rights, and they don't protect the GC or its payment bond surety.
  • North Carolina: by statute, owner payment to the contractor is not a condition precedent for paying a subcontractor, and an agreement to the contrary is unenforceable (N.C. Gen. Stat. § 22C-2).
  • Wisconsin: Wis. Stat. § 779.135 voids clauses making payment from the owner a condition precedent, but still allows clauses that delay payment until the prime is paid.
  • Illinois: 770 ILCS 60/21 says a clause conditioning the sub's payment on the owner's payment is not a defense to a mechanic's lien claim.
  • Texas: Business and Commerce Code Chapter 56 allows a "contingent payment clause" but limits it, for example where the owner's nonpayment is the GC's own fault or where enforcement would be unconscionable, and it can't be used against a mechanic's lien.

Many other states will enforce a clear pay-if-paid clause. Law firms publish 50-state surveys on contingent payment clauses (Kegler Brown's 2025 survey is one), and they're worth a look before you standardize your subcontract across states.

How do federal jobs handle pay-when-paid?

On federal construction, the Prompt Payment Act sets the floor. Under 31 U.S.C. § 3905, every federal construction contract must require the prime to put a clause in each subcontract obligating it to pay the sub for satisfactory work within 7 days out of amounts the agency pays the prime, with an interest penalty for late payment.

The prime can still withhold for cause, but it has to give the sub a written notice stating the amount, the reason under the subcontract and the fix needed, and copy the government. Retainage is allowed if the subcontract provides for it. Subs on federal jobs also have Miller Act payment bond rights, so a pay-if-paid clause is a weak shield there.

Many states have their own prompt payment acts for public and private work with similar pass-through deadlines. Check yours.

What should a GC do with these clauses?

If you're the GC, the clause is a backstop, not a payment plan. A few habits keep you out of the fight:

  1. Use clear language for what you mean. If you intend pay-when-paid, say "within 7 days after receipt" and add an outside date (for example, no later than 60 days after an approved pay app). An outside date makes the clause easier to defend as a timing term.
  2. Don't rely on pay-if-paid in states that void it. If your template is going into New York, California or North Carolina, assume the sub gets paid regardless.
  3. Pass money through fast when you get it. Subs talk. The GCs who pay within days of receiving owner funds get better pricing and better crews on the next bid.
  4. Tie retainage to the same rules. Retainage release is where most pay-when-paid fights end up. See our guide to retainage in construction.
  5. Track what's been billed, paid and owed per sub. If you can't show the owner paid you on a given line, you can't credibly invoke the clause.

What should a sub look for before signing?

If you're the sub, read the payment article twice:

  • Find the trigger words. "Condition precedent" or "only if paid" is pay-if-paid. Push to redline it to pay-when-paid with an outside date.
  • Ask about funding. On private work, ask for evidence the owner's financing is in place before you mobilize.
  • Protect your lien and bond rights. Know your notice deadlines. A pay-if-paid clause often can't take away lien rights in states like California and New York, but missing a notice deadline can.
  • Watch your lien waivers. Don't sign an unconditional waiver for money you haven't received. Our post on conditional vs unconditional lien waivers covers when to sign which.

How to keep sub payments from stalling

Most pay-when-paid arguments start with slow owner payments, and most slow owner payments start with a messy pay app. Clean schedules of values, backup attached the first time, and change orders approved before they're billed all shorten the cycle. Our playbook on how to get paid faster in construction walks through the steps.

That's where software helps. CooperBuild AI has full accounting built in (general ledger, accounts payable and accounts receivable), connects to QuickBooks Online, and supports online payments through Stripe. When owner payments, sub invoices and retainage live in one place, you can see which subs are due the day the owner's money lands, and your team can ask the CooperBuild AI assistants what's still owed on a job instead of digging through spreadsheets.

If you want to see it on your own jobs, start a free trial.

FAQ

What is the difference between pay-when-paid and pay-if-paid?

Pay-when-paid sets the timing: the GC pays the sub within a set or reasonable time after the owner pays, and still owes the sub if the owner never pays. Pay-if-paid makes owner payment a condition, so where it's enforceable the GC may never owe the sub if the owner doesn't pay.

No. New York and California courts have held pay-if-paid clauses unenforceable, and statutes in states like North Carolina, Wisconsin and Illinois void or limit them. Other states enforce them if the language is clear. Check your state's law with a construction attorney.

How long can a GC wait under a pay-when-paid clause?

Courts generally allow a reasonable time, which depends on the facts and the contract. On federal jobs the Prompt Payment Act requires payment within 7 days of the prime receiving the agency's payment, and many state prompt payment laws set their own deadlines.

Does a pay-if-paid clause stop a sub from filing a mechanic's lien?

Often not. California and New York treat pay-if-paid clauses as an improper waiver of lien rights, and Illinois and Texas statutes limit using them against lien claims. Subs still have to meet their own notice and filing deadlines.

Written by

Adam Hicks, Founder, CooperBuild AI

Get started

Run your next job in Cooper.

Start on free credit and run a real job this week, or book a 30-minute demo on your own spec set, estimate or card statement. Either way, no card and no contract.

$20 in free credits, no card needed