- What is progress billing in construction?
- How often do contractors submit progress billings?
- What is the difference between progress billing and milestone billing?
- Can you bill for stored materials in a progress billing?
- Does QuickBooks Online support progress billing?
By Adam Hicks, CooperBuild AI · November 13, 2026
Progress billing in construction means you bill the owner in stages as work gets done, instead of one invoice at the end. Most commercial jobs bill monthly against a schedule of values: you claim the percent complete on each line, subtract retainage and what you've already billed, and the owner pays the difference. Residential and small jobs often bill on milestones instead, like "dried in" or "rough-ins passed."
Done right, progress billing keeps cash moving with the work. Done sloppy, it gets your pay app kicked back and pushes payment out another month. Here's how it works and how to keep it clean.
What is progress billing in construction?
Progress billing is a payment setup where the contract sum gets paid out over the life of the job, based on how much work is in place. Each bill covers the work done since the last one, so you aren't carrying a whole job's labor and material on your own balance sheet.
It's the opposite of billing everything at completion. On anything longer than a few weeks, waiting until the end means you're basically financing the owner's project.
How does progress billing work?
On most commercial jobs the cycle looks like this:
- Set up the schedule of values. Break the contract sum into line items, by trade or phase, that add up to the contract total. See our schedule of values guide for how to build one that holds up.
- Agree on the billing date. Many contracts set a cutoff date each month and a deadline for submitting the pay application. Miss it and you can slide a full cycle.
- Measure percent complete. For each line, figure out how much of the work is actually in place as of the cutoff.
- Add stored materials if the contract allows it. Some contracts let you bill for material delivered and stored, on or off site, with backup like invoices and proof of insurance.
- Add approved change orders. Only executed change orders go on the bill. Pending ones don't.
- Subtract retainage and previous billings. What's left is the amount due this period.
- Submit with backup. Sub pay apps, lien waivers if your contract requires them, and anything else the owner or lender asked for.
- Owner or architect reviews it. They can approve, adjust, or reject lines they don't agree with.
What's the difference between progress billing and milestone billing?
Both are forms of billing in stages. The difference is what triggers the bill.
- Percent-complete billing bills on a calendar, usually monthly, for whatever percent of each line is done. It's common on commercial and public work with a schedule of values.
- Milestone billing bills when a defined stage is finished, like foundation complete, framing complete, or substantial completion. It's common on residential and smaller jobs.
Milestone billing is simpler to set up. Percent-complete billing tracks the work more closely and usually keeps cash flow steadier on long jobs, because you don't wait for a big stage to finish before you can bill.
A sub on r/GeneralContractor asked this exact question in April 2026: on big, months-long jobs, waiting on big lump payments plus 30-day terms hurt. The common answer from other contractors was monthly progress payments tied to a simple schedule of values.
How do you calculate a progress billing amount?
The basic math for each line on the schedule of values:
- Work completed to date = scheduled value × percent complete
- Plus stored materials (if allowed)
- Total completed and stored to date
- Minus retainage (the percentage your contract says)
- Minus previous billings
- = Amount due this period
Example: a $200,000 framing line is 40% complete. Work to date is $80,000. Last month you billed 25%, or $50,000. If the contract holds 10% retainage, earned less retainage is $72,000, previous billings less retainage were $45,000, so this period's billing on that line is $27,000.
Run that across every line and add it up. For how retainage builds up and gets released, see our retainage guide.
How do you avoid overbilling and underbilling?
Percent complete has to be honest. If you bill ahead of the work, you're overbilled. That looks like extra cash today, but it's really money you owe the job in work, and bonding companies and lenders watch it. If you bill behind the work, you're underbilled, and you're financing the job out of your own pocket.
A few habits that help:
- Walk the job before you bill. Percent complete should come from the field, not from what the budget says you've spent.
- Compare billed vs earned every month. That comparison is the core of a WIP report.
- Front-load carefully. Putting too much value on early line items gets noticed, and owners and architects push back on it.
- Keep your subs' percents in line with yours. If you bill the owner 60% on drywall, your drywall sub shouldn't be billing you 80%.
What gets progress billings rejected?
Most rejected pay apps come down to the same handful of problems:
- Percent complete the owner's rep doesn't agree with after walking the job
- Unexecuted change orders included in the bill
- Missing backup, like sub pay apps, stored material invoices, or required waivers
- Math errors between the schedule of values and the summary
- Submitted after the cutoff date in the contract
The fix is mostly process: one schedule of values everyone bills from, change orders logged the day they're signed, and a checklist of required backup that goes out with every bill. Our guide to getting paid faster covers the rest of the collection side.
Can you do progress billing in QuickBooks Online?
Yes, at a basic level. According to Intuit's help article "Set up and send progress invoices," you turn on progress invoicing under Account and settings on the Sales tab, then create invoices from an estimate. QuickBooks lets you bill the entire estimate, a percentage of it, or by line item, and you can create several progress invoices from the same estimate.
What it doesn't give you out of the box is the full construction picture: retainage tracking by line, stored materials, change orders rolling into the schedule of values, and billed vs earned compared to job costs. Plenty of GCs end up running those in spreadsheets next to QuickBooks.
How CooperBuild AI helps
Progress billing goes smoother when the schedule of values, change orders, job costs and accounting all live in one place. CooperBuild AI has full accounting built in (GL, AP and AR), schedules of values, change orders and job costing by cost code, plus integrated payments through Stripe so owners can pay online. It also connects to QuickBooks Online if that's where your books live. Assistants pick up action items from job chat, like "owner approved CO 7, add it to this month's billing," so they don't get lost before the cutoff.
If you want to see it on your own jobs, start a free trial.
FAQ
What is progress billing in construction?
Progress billing is billing the owner in stages as work gets done, instead of one invoice at the end. Most commercial jobs bill monthly against a schedule of values, claiming percent complete on each line minus retainage and previous billings.
How often do contractors submit progress billings?
Most commercial contracts call for monthly billing with a set cutoff date. Residential and small jobs often bill on milestones instead. Your contract sets the schedule, so check the payment terms before the first bill.
What is the difference between progress billing and milestone billing?
Progress billing usually means monthly billing for the percent of each line that's complete. Milestone billing means you bill when a defined stage is finished, like framing or substantial completion.
Can you bill for stored materials in a progress billing?
Only if your contract allows it. Many contracts let you bill for material delivered and stored, as long as you provide backup like invoices and proof of insurance.
Does QuickBooks Online support progress billing?
Yes. QuickBooks Online has a progress invoicing setting that lets you create multiple partial invoices from one estimate, by percentage or by line item. Retainage, stored materials and change order tracking usually need more than that.