- What are extended general conditions?
- When can a GC claim extended general conditions?
- How do you calculate extended general conditions?
- Daily rate or actual cost: which should you use?
- What do owners push back on?
- How do you set up a job so the claim holds up?
- Keep the delay record tied to the job
- FAQ
- What are extended general conditions in construction?
- How do you calculate extended general conditions?
- What is the difference between extended general conditions and the Eichleay formula?
- Can a GC recover extended general conditions if the delay was concurrent?
- Do subcontractors get extended general conditions too?
By Adam Hicks, CooperBuild AI · November 24, 2026
Extended general conditions are the extra time-related field costs a general contractor carries when a job runs past its planned finish: the superintendent and PM, the trailer, temp power, equipment rental and site services for every added day. When an owner-caused delay pushes the critical path, a GC can usually recover them by turning general conditions into a daily rate and multiplying it by the days of compensable delay, provided the contract allows it and notice went out on time.
This guide covers what counts, how to calculate the claim, what owners push back on and what to set up on day one so the number holds up. If you need the basics first, read general conditions in construction.
What are extended general conditions?
They're the same general conditions you priced in your bid, just for more time. Contractors also call them extended field overhead or time-related delay costs.
The key word is time-related. Some general conditions scale with time, like staff salaries, the trailer, temporary toilets, temp utilities, rented equipment and weekly cleanup. Others are one-time or quantity-based, like mobilization, permits or a final clean. Only the time-related items grow when the job runs long, so only they belong in an extended general conditions claim.
Keep them separate from home-office overhead. Field overhead exists because this one project exists. Company overhead, like office rent and accounting, is a different claim, usually priced with the Eichleay formula when work is suspended.
When can a GC claim extended general conditions?
Three things usually have to line up:
- The delay is compensable. It was caused by the owner or someone the owner is responsible for, like the design team, and the contract doesn't limit you to time only.
- The delay hit the critical path. Late owner decisions on work with float don't extend the finish date, so they don't extend your field costs.
- You followed the notice rules. Most contracts require written notice within a set number of days. Late notice is one of the most common reasons these claims fail. See construction delay notice for what to send.
Two contract clauses can shut the door. A no damages for delay clause may limit you to a time extension, subject to exceptions that vary by state. And if your own delays overlap the owner's, concurrent delay rules often give you time but no money for those days.
How do you calculate extended general conditions?
The most common method is a daily rate. In a Florida Construction Legal Updates summary by attorney David Adelstein, two boards of contract appeals describe it the same way: divide total general conditions costs by the total days of contract performance, then multiply by the days of compensable delay. The alternative is to use the actual field costs incurred during the delay period.
Step 1: Pull your time-related general conditions. Use job cost records, not the estimate. Separate time-related lines from fixed and quantity-based ones.
Step 2: Divide by the days of performance. That gives you a daily field overhead rate for the job.
Step 3: Multiply by the compensable delay days. Use the days your schedule analysis supports, not the total overrun.
Step 4: Remove anything already paid. If a change order already included extended time or general conditions markup, deduct it so you don't bill twice.
The same article cites MCI Constructors, Inc. (DCCAB No. D-924, 1996), where the board found about $303,625 in time-related general conditions over an 802-day contract period. That's a daily rate of about $378.58. Multiplied by 252 delay days, it came to about $95,402, which the board then reduced for overhead markup already included in other change orders.
Daily rate or actual cost: which should you use?
Daily rate (averaging). Simple and easy for an owner to follow. The weakness is that it assumes your field costs were flat across the job. If the delay happened during a light stretch with a small crew, an average can overstate the cost, and an owner's consultant will say so.
Actual cost during the delay window. More accurate when staffing changed. You show who was on site, what was rented and what you paid during the specific delay period. It takes better records, but it's harder to argue with.
Many GCs calculate both and lead with the one their records support best.
What do owners push back on?
Expect these challenges and get ahead of them:
- Underbid general conditions. In the Clark Construction Group appeal (GAOCAB No. 2003-1, 2004) summarized in the same article, the contractor had underbid general conditions. The board took the underbid amount out of the actual costs before computing the daily rate, so the contractor wasn't rewarded for a low bid.
- Costs that aren't time-related. One-time items in the daily rate inflate it. Strip them out first.
- Double counting. Field overhead in the direct cost calculation can't also sit in a G&A pool, and time already priced into change orders comes out.
- Weak schedule proof. Without a critical path analysis showing the owner's delay drove the finish date, the days aren't compensable. A time impact analysis is the usual tool.
How do you set up a job so the claim holds up?
Most of the work happens before anything goes wrong:
- Build general conditions from the schedule. Price them as a weekly or monthly cost times the duration, with time-related lines clearly tagged. That gives you a daily rate on day one.
- Code field costs to the job. Supervision, rentals and temp facilities need their own cost codes so you can pull actuals for any date range.
- Keep daily reports current. Record who was on site, what was blocked and why. A construction daily report is the record a board or mediator will ask for.
- Send notice fast. Track the deadline for each delay event and log what you sent.
- Price time into change orders. When a change adds days, include the added general conditions in that change order rather than saving it for a claim later.
Keep the delay record tied to the job
Extended general conditions claims come down to records: the daily rate, the field costs by date, the notices and the schedule. When those live in separate spreadsheets, rebuilding them months later is slow and easy to challenge.
CooperBuild AI keeps estimates, schedules, daily reports, change orders, job costs and built-in accounting (GL, AP and AR) in one system, and connects to QuickBooks Online. Your general conditions budget, the actual field costs and the delay record stay on the same job, so the daily rate is there when you need it.
If you want your next job set up so a delay claim is a report instead of a rebuild, get started with free credits, no credit card needed.
FAQ
What are extended general conditions in construction?
Extended general conditions are the added time-related field costs a contractor incurs when a job runs past its planned finish, such as supervision, the field office, temporary utilities, equipment rental and site services for the extra days or weeks.
How do you calculate extended general conditions?
The common method is a daily rate: total time-related general conditions divided by the days of contract performance, multiplied by the days of compensable delay. Where records allow, you can instead use the actual field costs incurred during the delay period.
What is the difference between extended general conditions and the Eichleay formula?
Extended general conditions cover field overhead tied to the one project, like the superintendent and trailer. The Eichleay formula is used for unabsorbed home-office overhead, the company costs that keep running while a job is suspended.
Can a GC recover extended general conditions if the delay was concurrent?
Often not in full. When owner and contractor delays overlap on the critical path, many contracts and courts give a time extension without money for the overlapping days, so you need a schedule analysis that separates the delay windows.
Do subcontractors get extended general conditions too?
They can claim their own extended field costs if their subcontract allows compensable delay and they give timely notice. Check the flow-down and any no damages for delay clause before pricing a sub's claim or passing one up to the owner.
This article is general information for contractors, not legal or accounting advice. Delay recovery depends on your contract and jurisdiction, so review claims with construction counsel.