- What is a construction change directive?
- Can a contractor refuse a change directive?
- Who signs a change directive?
- Can you bill a change directive on a pay application?
By Adam Hicks, CooperBuild AI · November 24, 2026
A construction change directive is a written order from the owner telling the GC to proceed with changed work before the price or time impact has been agreed. It keeps the job moving, but it doesn't settle the money. Your job when one arrives is to start the work, put your position in writing, and track every dollar and day so the directive turns into a signed change order you can bill.
Directives usually show up when an owner needs work done now and the change order negotiation is stuck. Handle them loosely and you build the work, then argue about the price for months.
What is a construction change directive?
A change directive (often shortened to CCD, or called a field directive or directed change) is a one-sided instruction. The owner, sometimes through the architect or owner's rep, orders a change in the work and tells you to proceed. Your signature isn't needed for it to take effect.
Many standard-form general conditions and custom contracts include a directive mechanism, and so does federal work. Under the FAR Changes clause, 52.243-4 (opens in a new tab), the contracting officer may make changes within the general scope of the contract by written order, and must then make an equitable adjustment if the change affects your cost or time. ConsensusDocs 200 has a version too, which it calls an interim directed change (SMACNA Contracts Bulletin #98 (opens in a new tab)).
Wording and deadlines differ by contract, so read your change and claims sections before the first directive lands.
What is the difference between a change directive and a change order?
The difference is agreement. A change order is signed by both sides and fixes the new contract sum and time. A change directive orders the work first and leaves price and time to be settled later, usually by a change order once the numbers are agreed.
| Change order | Change directive | |
|---|---|---|
| Price and time | Agreed before it's signed | Open when issued |
| Your signature | Required | Not required to take effect |
| Your obligation | Build to the agreed terms | Proceed, then document and negotiate |
| How it ends | Already final | Converted to a change order, or becomes a claim |
If you're still at the pricing stage, our construction change order process guide covers the steps from change order request to signature.
Do you have to proceed with a change directive?
Usually, yes. Most contracts that allow directives require the contractor to proceed promptly, and refusing can be treated as a breach. On federal work, the Disputes clause, FAR 52.233-1(i) (opens in a new tab), requires the contractor to proceed diligently with performance pending final resolution of any request for relief, claim or appeal.
There are limits. A directive is meant for changes within the general scope of the contract. Construction lawyers point to the cardinal change doctrine for changes so large they amount to abandoning the original contract (New York Construction Law (opens in a new tab)). That's a call for your attorney, not your super. In practice, the safer move is to proceed under protest and preserve your rights in writing.
What should a GC do when a change directive arrives?
Treat the first 48 hours as the most important part of the change.
- Log it the day it arrives. Give it a number in your change order log with the date, who issued it, the scope and the drawings or RFIs it references.
- Read the pricing basis. Some directives state a lump sum, unit prices or a cost-plus method. Note whether you agree with that method.
- Respond in writing. Acknowledge receipt, say you are proceeding, state that you expect cost and schedule impacts, and reserve your right to an adjustment. If you disagree with the stated price or method, say so and say you are proceeding under protest.
- Check your notice deadline. Under FAR 52.243-4(e), the contractor must assert its right to an adjustment within 30 days of receiving a written change order, unless the government extends that period. Private contracts set their own windows, and some are much shorter.
- Open a separate cost code. Directed work should never be buried in base-contract labor or materials.
- Push it down to your subs. Issue a written directive to every affected subcontractor with the same scope, and ask them to track their own costs separately.
How do you track costs on directed work?
Your documentation is the price. If the owner or architect ends up deciding the amount, they work from what you can prove, so track it as if you were billing time and materials.
- Daily labor tickets with names, trades, hours and the work performed, signed by the owner's rep where possible. Our guide to time and material tickets covers what to capture.
- Material and equipment with invoices, delivery tickets and rental records tied to the directive number.
- Sub costs backed by their own tickets, not just a lump-sum number.
- Schedule impact shown against the current schedule update, not argued after the fact.
- Photos of existing conditions before you start and progress as you go.
Track markup separately too. Your contract may set the overhead and profit you can add to directed work; see change order markup for how those limits usually work.
Can you bill a change directive before it becomes a change order?
It depends on your contract. Some contracts let you bill the undisputed or determined portion of directed work on your monthly pay application while the final amount is negotiated. ConsensusDocs 200, for example, requires the owner to pay 50% of the contractor's actual incurred costs when the cost of an interim directed change is disputed, with the rest left to the dispute process (SMACNA (opens in a new tab)).
If your contract allows it, add the directive as its own line on the schedule of values instead of folding it into existing lines, so the owner can trace it. If it doesn't, keep the directive in your pending changes and report it to the owner every month so the open dollars stay visible. Either way, don't let directed work sit unbilled and untracked until closeout.
How does a change directive become a change order?
Once the work is done, or far enough along to price, submit your costs, markup and time request with backup. If the owner agrees, sign a change order that closes the directive and adjusts the contract sum and time. If you can't agree, the directive becomes a claim under your contract's dispute process.
The cleaner your daily records, the shorter that negotiation. Directives that close fast usually have three things: a same-day written response, tickets signed while the work was happening, and a cost code that shows nothing else.
Where CooperBuild AI fits
Directives get expensive when the field, the change log and the books live in different places. CooperBuild AI is an AI-native operating system for general contractors: the estimate becomes the live project, and changes, commitments, vendor bills, pay apps and job costs hang off the same line items instead of a stack of Procore, QuickBooks and spreadsheets. It includes built-in accounting (GL, AP and AR), connects to QuickBooks Online and supports integrated payments through Stripe.
If you want every open directive and its costs in one place, start a 14-day free trial (opens in a new tab).
FAQ
What is a construction change directive?
A construction change directive is a written order from the owner directing the contractor to proceed with a change in the work before the price or time adjustment has been agreed. It is usually converted to a change order once the parties agree on the numbers.
Can a contractor refuse a change directive?
Usually not, if the change is within the general scope of the contract and the contract allows directives. Refusing can be treated as a breach. The safer approach is to proceed under protest, reserve your rights in writing and follow the contract's claim process.
Who signs a change directive?
The owner, and often the architect or owner's representative, signs it. The contractor's signature is not needed for it to take effect, although the contractor can sign to show it agrees with the proposed price and time.
Can you bill a change directive on a pay application?
Only if your contract allows it. Some contracts let you bill the undisputed or determined amount while the rest is negotiated. If yours doesn't, track the directive separately and bill it once it becomes a signed change order.
This article is general information, not legal advice. Change and claims provisions vary by contract and jurisdiction; confirm your rights and deadlines with a construction attorney.