- What is force account work?
- When do owners use force account?
- How is force account work paid?
- What records do you need for force account work?
- How do you keep force account costs from slipping?
- Is force account the same as T&M?
- FAQ
- What does force account mean in construction?
- When is force account work used?
- How are equipment rates set for force account work?
- Can a GC bill supervision on force account work?
- Track extra work on the same record as the job
By Adam Hicks, CooperBuild AI · November 27, 2026
Force account work is extra work paid at actual cost plus set markups, instead of at a bid unit price or an agreed lump sum. On public jobs, especially state DOT highway work, the owner orders force account when the scope is unclear or the two sides can't agree on a price. The contractor gets paid only for the labor, equipment and materials it can prove, so daily records decide what you collect.
What is force account work?
In a construction contract, force account is a payment method for changes. Caltrans describes it as "adding specified markups to the actual cost of labor, equipment, and material used to perform the extra work" (Caltrans Construction Manual, 3-903 (opens in a new tab)).
It is the public-works cousin of time and material tickets, with markups, equipment rates and paperwork written into the agency's specifications.
The term has a second meaning. Federal highway rules define force account as "the direct performance of highway construction work" by a state DOT, county, railroad or utility with its own forces (23 CFR 635.203 (opens in a new tab)). This article is about the contractor meaning: extra work billed at cost plus markup.
When do owners use force account?
Usually as a last resort. Michigan DOT's construction manual says force accounts are for rare cases where the contractor and engineer can't agree on a price, the scope can't reasonably be determined, the work starts before prices are negotiated, or other payment methods are impractical. It adds a line every PM should remember: "Any work started before cost has been agreed upon is a Force Account" (MDOT (opens in a new tab)).
TxDOT's force account job aid says the same in fewer words: the method is used "when the work scope is unknown or an established unit price for the work is unknown" (TxDOT (opens in a new tab)).
On a unit price contract, the usual order is: pay at existing bid items if they fit, negotiate a new price if they don't, and fall back to force account when neither works.
How is force account work paid?
Each agency's spec sets its own rules, so read yours before the first shift. The common structure looks like this:
- Labor. Actual wages and fringes for the workers and foreman on the extra work, plus a markup or surcharge. Michigan pays actual on-site labor cost plus 55 percent for road work or 60 percent for bridge work, a unified markup that covers bonds, insurance, taxes and other costs (MDOT (opens in a new tab)).
- Materials. Invoice cost delivered, plus a markup. Michigan adds 15 percent on materials incorporated into the work (MDOT (opens in a new tab)).
- Equipment. Owned equipment at a published rate, most often the EquipmentWatch Blue Book. Michigan and TxDOT both point to it for verifying rates.
- Subcontracted work. The sub's force account cost plus an administrative markup for the prime. Caltrans, for example, applies a 10 or 15 percent administrative markup on owner-operator invoices, depending on whether the job has a time-related overhead bid item (Caltrans 3-903E (opens in a new tab)).
What isn't paid matters just as much. New Hampshire's spec says no part of the salary or expenses of anyone above the grade of foreman is payable, because supervision and office costs are covered by the markup (NHDOT Section 109 via BuildSpec (opens in a new tab)). If your estimating or PM time is the real cost of the change, a lump sum may be the better deal.
What records do you need for force account work?
Enough to tie every hour and dollar to a payroll, an invoice or a rate book. Agencies spell this out:
- A work plan before you start. Michigan requires a contractor proposal and an agreed work plan covering crew, equipment, materials, schedule and estimated cost, and says items not in the approved plan are ineligible for payment.
- A daily record, signed the same day. TxDOT uses a daily force account report signed by the contractor. Caltrans asks its inspectors to reach a tentative agreement with the contractor's foreperson on labor, equipment and materials at the end of each shift, or no later than the next one.
- Labor by name, classification, hours and rate. NHDOT lists name, classification, date, daily hours, total hours, rate and extension for every laborer, operator and foreman, backed by certified payrolls.
- Equipment by make, model, year and hours. TxDOT checks each unit's description against EquipmentWatch rates.
- Material invoices and transport charges. Material taken from your own stock needs an affidavit of cost in New Hampshire.
- Records kept for audit. NHDOT keeps force account cost records open to audit for at least three years after acceptance.
TxDOT's job aid shows why hours need care. If a laborer worked eight hours that day but only four on the extra work, payroll shows eight and only four are payable.
How do you keep force account costs from slipping?
The money is usually lost in small gaps. A few habits close them.
Get the order in writing before the crew moves. An electrical sub on r/Construction (opens in a new tab) said he lost about $4,000 in a month on extra work that was never documented in time. One reply: require a written order to proceed from an authorized person before any time goes in.
Confirm equipment rates up front. A small DOT contractor on r/Construction (opens in a new tab) described approved, completed work held up because the DOT wanted EquipmentWatch rate data he couldn't easily get. Commenters said the DOT should have confirmed the rates before authorizing the work. Ask the inspector which rate source applies, and settle it before the work starts. Our guide to equipment cost per hour explains what those rates should cover.
Watch the estimate on the change order. Caltrans shows force account on the authorizing change order as an estimate, and lets payment run over it by up to 100 percent of the estimate or $15,000, whichever is smaller. Beyond that, a supplemental change order is needed. Track spend against it weekly.
Price the paper daily. Each signed daily record should be priced and added to the change order log the same week. Agencies may pay progress on force account; Michigan allows bi-weekly payments once the daily records for that period are signed.
Flow the rules down to subs. If the owner pays your sub's work at cost plus a set markup, your subcontract should say the sub's force account billing follows the same records and rates. A T&M rate sheet agreed during buyout helps, as long as it matches the prime spec.
Is force account the same as T&M?
They work the same way: count hours, equipment and materials, then price them at agreed rates. On private work, T&M rates are usually negotiated in a rate sheet. On public work, force account markups, rate books and forms are usually fixed by the owner's specifications.
This article is general information, not legal advice. Force account rules vary by agency and contract, so read your specifications and check with a construction attorney on disputes.
FAQ
What does force account mean in construction?
Force account is a way of paying for extra work at the actual cost of labor, equipment and materials plus markups set in the contract. In federal highway rules, the term also means an agency or utility doing work with its own forces.
When is force account work used?
It is used when the scope of extra work can't be defined, no bid unit price fits, or the owner and contractor can't agree on a lump sum. Michigan DOT treats any work started before cost is agreed as force account.
How are equipment rates set for force account work?
Most state DOTs use a published rate source for owned equipment, often the EquipmentWatch Blue Book. Rented equipment is usually paid at invoice cost plus a markup. Confirm the rate source before work starts.
Can a GC bill supervision on force account work?
Usually not above the foreman level. Many specs, such as New Hampshire's, say the salary or expenses of anyone above foreman aren't payable because the markup covers supervision and overhead.
Track extra work on the same record as the job
Force account rewards contractors whose daily records, rates and change orders line up. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate becomes the live project, and change orders, subcontracts, pay apps, payments and the general ledger hang off the same deliverables. It has built-in accounting (GL, AP and AR), connects to QuickBooks Online, and takes payments through Stripe, so extra work doesn't live in a separate spreadsheet.
If you want change orders and job cost on one record, start a 14-day free trial (opens in a new tab).