  1. What goes into equipment cost per hour?
  2. How do you calculate an hourly rate for owned equipment?
  3. What does a worked example look like?
  4. Why is utilization the number that matters most?
  5. Should you use published equipment rate schedules?
  6. How do standby rates work?
  7. How do you use the rate on bids, T&M and change orders?
  8. FAQ
  9. How do you calculate equipment cost per hour?
  10. Should operator wages be included in the equipment rate?
  11. What is a standby rate for construction equipment?
  12. Can I use the Army Corps of Engineers equipment rates on private jobs?
  13. Price equipment on the same record as the job

By Adam Hicks, CooperBuild AI · November 25, 2026

Equipment cost per hour is what it really costs you to own and run a machine for one hour of use: ownership costs (depreciation, cost of money, insurance, taxes, storage) plus operating costs (fuel, lube, repairs, tires or undercarriage), divided by the hours the machine actually works. Operator labor, overhead and profit are added on top. The number you divide by, real annual utilization, matters as much as anything you add up.

Plenty of contractors who own a skid steer, excavator or lift price it off a rental-yard rate or "the loan payment divided by something." That works until the machine sits for a month, needs a rebuild, or gets challenged on a change order. This guide walks through a defensible equipment cost per hour, a worked example, and how to use the rate on bids, T&M tickets and claims.

What goes into equipment cost per hour?

Split every cost into two buckets. The federal cost rules for construction contracts use the same split, describing equipment costs as "ownership and operating costs" (FAR 31.105(d)(2) (opens in a new tab)).

Ownership costs happen whether the machine runs or not:

  • Depreciation. Purchase price (including delivery and attachments) minus expected resale value, spread over the hours you expect to own it.
  • Cost of money. Interest on the loan, or the return you give up by tying cash up in iron.
  • Insurance and property tax on the unit.
  • Registration, storage and yard costs you can trace to the machine.

Operating costs only happen when it runs:

  • Fuel, at your real burn rate and current price.
  • Lube, filters and fluids.
  • Repairs and maintenance, including the major repairs you know are coming.
  • Tires, tracks, undercarriage and wear parts such as bucket teeth and cutting edges.

Keep operator labor out of the equipment rate. The operator is labor, priced at a fully burdened rate (see our labor burden rate guide). Federal guidance makes the same point: labor, mobilization, demobilization, overhead and profit "are generally not reflected" in equipment rate schedules and need separate consideration (FAR 31.105 (opens in a new tab)).

How do you calculate an hourly rate for owned equipment?

  1. Set annual utilization. Use last year's actual metered or timecard hours, not the hours you hope to run.
  2. Total the annual ownership costs from the list above.
  3. Divide ownership by annual hours to get ownership cost per hour.
  4. Estimate operating cost per hour from fuel burn, maintenance records and wear-part history.
  5. Add the two. That's your equipment cost per hour, before operator, overhead and profit.

If you don't have records yet, start with the machine's maintenance schedule and fuel data from your dealer or telematics, then replace estimates with actuals after six to twelve months.

What does a worked example look like?

Here's an illustrative compact excavator. Every figure below is a placeholder for the math, not a benchmark. Use your own purchase price, resale estimate, insurance and fuel numbers.

  • Purchase price with attachments: $150,000
  • Expected resale after 5 years: $45,000
  • Annual utilization: 1,200 hours

Ownership per year:

  • Depreciation: ($150,000 − $45,000) ÷ 5 = $21,000
  • Cost of money: 7% on the average investment of $97,500 = $6,825
  • Insurance and property tax: $3,000
  • Registration and storage: $600
  • Total: $31,425, or $26.19 per hour at 1,200 hours

Operating per hour:

  • Fuel: 4 gallons × $4.00 = $16.00
  • Repairs and maintenance: $9.00
  • Tracks and wear parts: $3.00
  • Lube, filters and fluids: $1.50
  • Total: $29.50 per hour

Equipment cost per hour: $55.69.

Now drop utilization to 800 hours. Ownership becomes $31,425 ÷ 800 = $39.28 an hour, and the total jumps to $68.78. Same machine, same fuel, about 24% more cost per hour, because the fixed cost is spread over fewer hours. That's why utilization is the first number to check every year.

Why is utilization the number that matters most?

Ownership cost is fixed for the year. Every hour the machine sits in the yard pushes the hourly cost of every hour it does work. A rate built on an optimistic utilization quietly underprices every job that uses it.

Track hours per unit from timecards or telematics, compare them to the hours in your rate, and reset the rate when they drift. If a machine can't reach a reasonable utilization, renting may be cheaper than owning, and your rate math will show it.

Should you use published equipment rate schedules?

On some work you'll have to. Public schedules exist so owners and contractors don't argue from scratch:

  • The U.S. Army Corps of Engineers EP 1110-1-8, the Construction Equipment Ownership and Operating Expense Schedule, publishes predetermined ownership and operating rates for 12 geographic regions and a method for computing rates when the published ones don't fit (USACE (opens in a new tab)).
  • FEMA's Schedule of Equipment Rates covers applicant-owned equipment on disaster recovery work, and states that standby equipment costs are not eligible (FEMA (opens in a new tab)).

On federal work, FAR says actual cost data from your accounting records is used when you can determine both ownership and operating costs for each piece of equipment; otherwise the agency may specify a schedule (FAR 31.105(d)(2) (opens in a new tab)). Private contracts vary. Many say how equipment on changes is priced, so read that clause before you send a rate sheet.

How do standby rates work?

Standby is equipment on site but idle because of a delay or suspension you didn't cause. Ownership costs keep running, but fuel and wear mostly don't, so a standby rate is usually built from ownership cost only, not the full operating rate.

On federal contracts, during a suspension of work under a contract clause the ownership allowance can't exceed the standby cost set by the schedule or the contract (FAR 31.105(d)(2) (opens in a new tab)). For the notice and documentation side, see our guides to the suspension of work clause and construction delay notices.

How do you use the rate on bids, T&M and change orders?

  • Bids. Equipment cost per hour times estimated hours goes into direct cost, then your markup covers overhead and profit (see markup vs margin).
  • T&M tickets. List each unit, hours used and the rate, separate from operator labor, on the T&M ticket the field signs that day.
  • Change orders. Apply the markup the contract allows (see change order markup), and keep the backup: purchase records, utilization history and repair logs.
  • Job costing. Charge equipment hours to jobs at the rate, then compare what the rate recovered with what the machine actually cost for the year.

This article is general information, not accounting, tax or legal advice. Contract terms, agency rules and tax treatment vary, so confirm with your accountant or attorney.

FAQ

How do you calculate equipment cost per hour?

Add annual ownership costs (depreciation, cost of money, insurance, taxes, storage) and divide by the hours the machine actually works in a year. Then add operating cost per hour for fuel, lube, repairs and wear parts.

Should operator wages be included in the equipment rate?

Usually not. Price the operator as labor at a fully burdened rate and keep it separate from the machine rate. Federal guidance notes labor is generally not reflected in equipment rate schedules.

What is a standby rate for construction equipment?

A standby rate covers equipment that is on site but idle because of a delay or suspension. It is usually built from ownership costs only, since fuel and wear mostly stop when the machine isn't running.

Can I use the Army Corps of Engineers equipment rates on private jobs?

You can use them as a reference if the contract allows, but private contracts set their own rules for pricing equipment on changes. Read the changes clause, and keep your own cost records as backup.

Price equipment on the same record as the job

An equipment rate only pays off if it reaches the estimate and then shows up in the job cost. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate becomes the live project, and vendor quotes, pay apps, payroll and the general ledger hang off the same deliverables. It includes built-in accounting (GL, AP and AR), connects to QuickBooks Online, and takes payments through Stripe. Stop stacking Procore, QuickBooks and a spreadsheet to find out what your iron really cost.

Start a free trial of CooperBuild AI and run your next estimate on the same record as the job.

Written by

Adam Hicks

Get started

Run your next job in Cooper.

Start on free credit and run a real job this week, or book a 30-minute demo on your own spec set, estimate or card statement. Either way, no card and no contract.

$20 in free credits, no card needed