- What is a no damages for delay clause?
- What costs does the clause actually take away?
- Are no damages for delay clauses enforceable?
- What are the common exceptions?
- How do GCs handle a no damages for delay clause?
- FAQ
- What is a no damages for delay clause?
- Are no damages for delay clauses enforceable?
- What are the exceptions to a no damages for delay clause?
- Do I still need to give delay notice if the contract has a no damages for delay clause?
- Can a GC put a no damages for delay clause in a subcontract?
- Keep the delay record while the job is running
By Adam Hicks, CooperBuild AI · November 17, 2026
A no damages for delay clause says that if the owner (or, in a subcontract, the GC) delays your work, your only remedy is more time, not more money. Most U.S. states enforce these clauses, but courts carve out exceptions, and a growing list of states void them on public jobs and, in a few states, on private jobs too.
For a small or mid-size GC, this one clause decides who pays for extra weeks of supervision, trailers, equipment and insurance when the job runs long through no fault of yours. This guide covers what the clause does, where it is not enforced, the common exceptions, and how to bid, negotiate and document a job that has one.
What is a no damages for delay clause?
It is a risk-shifting provision. Long International (opens in a new tab) explains that it tries to stop a contractor from recovering time-related costs from the owner, even when the owner caused the delay, and usually leaves a time extension as the contractor's only relief. The same clause shows up one tier down, where a GC uses it to block delay claims from its subcontractors.
A typical version, as summarized by Construction Business Owner (opens in a new tab), says the contractor cannot recover damages or added costs for delay and that a time extension is its "sole and exclusive remedy."
What costs does the clause actually take away?
It targets time-related costs, not changed work. If a job runs eight extra weeks because the owner was late with design decisions, the clause is aimed at the cost of those weeks: site supervision, the project manager's time, temporary facilities, equipment rental, insurance and home-office overhead. On most jobs that is your general conditions budget running past its planned duration.
It does not usually erase a time extension. That matters because the extension still protects you from liquidated damages for the owner's days.
Courts can also separate delay damages from other price adjustments. In Southern Seeding Service v. W.C. English (N.C. Ct. App. 2011), summarized by North Carolina Lawyers Weekly (opens in a new tab), a subcontract had both a no damages for delay clause and an equitable adjustment clause for unit prices if the work ran past the planned completion date. The court held that the delay clause did not block the separate price adjustment.
Are no damages for delay clauses enforceable?
In most states, yes, with exceptions. Smith Currie (opens in a new tab) notes that most jurisdictions recognize the clauses, then lists states that limit them by statute.
Some examples, straight from the statutes:
- North Carolina: N.C. Gen. Stat. § 143-134.3 (opens in a new tab) bars enforcing language that forbids or limits damages for delays caused solely by a public owner or its agent.
- Minnesota: Minn. Stat. § 15.411 (opens in a new tab) voids clauses in public works contracts that waive recovery for delay, disruption or acceleration caused by the public entity, while still allowing notice requirements and reasonable liquidated damages.
- Virginia: Va. Code § 2.2-4335 (opens in a new tab) voids public contract provisions that bar recovery for unreasonable delay caused by the public body.
- Ohio: Ohio Rev. Code § 4113.62(C) (opens in a new tab) voids provisions that waive liability for delay caused by the owner's act or failure to act, and extends the same protection to subcontractors for owner or contractor delay.
- California: according to the Woods Aitken 50-state survey (opens in a new tab), Cal. Pub. Cont. Code § 7102 makes the clauses unenforceable on public works when the delay is unreasonable and was not within the parties' contemplation.
Smith Currie also lists Colorado, Kansas, Louisiana, Missouri, New Jersey and Oregon as limiting the clause on public contracts, and Kentucky and Washington as limiting it on both public and private work under certain circumstances. Each statute is worded differently, so read the one for your state before relying on it.
What are the common exceptions?
Even where the clause is enforceable, courts often refuse to apply it in certain situations. Smith Currie lists the most common:
- Delay caused by active interference, fraud, misrepresentation, bad faith or gross negligence by the party relying on the clause.
- Delay so long that the delayed party would have been justified in abandoning the contract.
- Delay the parties did not contemplate when they signed.
- Delay that results from a breach of a fundamental obligation of the contract.
New York is a good example of how narrow these can be. A New York appellate court in Landis & Gyr Powers v. Berley Industries, quoting earlier cases (opens in a new tab), said the clauses are enforceable unless the delays were not contemplated or resulted from intentional wrongdoing, gross negligence or willful misconduct. The subcontractor in that case could not raise a factual issue on either point and lost its delay claim.
Construction Business Owner adds one more practical point: the owner still has to grant time extensions when they are due, and refusing them can make the clause unenforceable. Forcing you to finish on the original date despite owner delays can also start to look like constructive acceleration.
How do GCs handle a no damages for delay clause?
Start at bid time, not when the job is already late.
- Find it before you price. Search the general conditions and supplementary conditions for "sole remedy," "sole and exclusive remedy" and "no damages." Long International calls the clause a warning sign of financial trouble ahead for a bidding contractor.
- Price the risk or qualify your bid. If you cannot negotiate the clause out, carry extra time-related cost or list it in your bid exclusions and qualifications.
- Negotiate a narrower version. Construction Business Owner suggests limiting the clause by type of damage, type of delay, or the length of delay it covers, for example allowing recovery after a set number of days of owner delay.
- Match it in your subcontracts. If your owner contract bars delay damages, a subcontract that lets subs claim them leaves you in the middle. Check whether your state's statute protects subs, as Ohio's does.
- Keep giving notice. None of the statutes above void notice requirements. Send a written construction delay notice for every owner delay, on time, even if you think the clause bars money. Notice keeps your time extension and preserves an exception argument.
- Document cause and cost while it happens. The exceptions turn on facts: was the delay contemplated, how long did it run, did the owner interfere? Daily reports, meeting minutes, schedule updates and day-by-day general conditions costs are the evidence.
Delays rarely come one at a time, so also read up on concurrent delay, which owners often raise alongside this clause.
This is general information, not legal advice. Enforceability depends on your contract language and your state, so talk to construction counsel before you sign or file a claim.
FAQ
What is a no damages for delay clause?
A no damages for delay clause is a contract provision that limits a contractor's remedy for owner-caused delay to a time extension, so the contractor cannot recover extra time-related costs.
Are no damages for delay clauses enforceable?
In most states they are enforceable, but courts recognize exceptions, and several states void them on public contracts. Ohio, Kentucky and Washington limit them on private work too under certain circumstances.
What are the exceptions to a no damages for delay clause?
Common exceptions include delay caused by active interference or bad faith, delay so long it amounts to abandonment, delay the parties did not contemplate, and delay from a breach of a fundamental contract obligation.
Do I still need to give delay notice if the contract has a no damages for delay clause?
Yes. Notice preserves your right to a time extension, which protects you from liquidated damages, and it keeps open any argument that an exception applies.
Can a GC put a no damages for delay clause in a subcontract?
Yes, and many do. Some state statutes, like Ohio's, void these clauses in subcontracts when the owner or contractor caused the delay, so check your state's law.
Keep the delay record while the job is running
Whether this clause holds up usually comes down to records: notices sent on time, daily reports, schedule updates and general conditions costs tracked by day. CooperBuild AI keeps project chat, tasks and job costs in one place, and its assistants can pick up action items, like "send delay notice for the late owner selections," from the team's conversation so they are not forgotten. It includes built-in accounting with GL, AP and AR, connects to QuickBooks Online and supports integrated payments through Stripe.