- What is a unit price contract in construction?
- Who carries the risk in a unit price contract?
- What happens if quantities overrun on a unit price contract?
- How do you bill a unit price contract?
- Keep the unit price and the field quantity on one record
By Adam Hicks, CooperBuild AI · November 27, 2026
A unit price contract pays the contractor a fixed price for each unit of work actually installed, such as a cubic yard of excavation, a linear foot of pipe or a ton of asphalt, instead of one lump sum. The owner's bid quantities are estimates. You get paid for measured quantities, so your margin depends on how you build each unit price and how well you track what goes in the ground.
This guide covers how a unit price contract works, how to bid the unit prices, what happens when quantities overrun or underrun, and how to bill measured work without leaving money on the table.
What is a unit price contract?
In a unit price contract, the bid form lists work items, an estimated quantity for each, and a blank for your price per unit. Your bid total is each unit price times the estimated quantity, added up. That total is used to compare bidders, but it is not what you get paid.
What you get paid is the unit price times the quantity measured and accepted in the field. If the estimate said 1,000 linear feet of storm pipe and you install 1,120, you bill 1,120, unless a clause in the contract says otherwise.
Unit price contracts are common on heavy civil, highway, utility and site work, where nobody knows the exact quantities until the work is done. Building GCs see them too: as unit price items inside a lump sum job (rock excavation, unsuitable soil removal, extra piles) or as unit prices a sub lists for adds and deducts.
For how this compares with other pricing models, see cost-plus vs lump sum contracts.
How is a unit price contract different from lump sum?
On a lump sum job, you carry the quantity risk. If you counted wrong, it's your problem. On a unit price job, the owner carries most of the quantity risk and you carry the cost risk per unit. If the unit costs you more to install than you priced it, you lose money on every unit, and more units means a bigger loss.
That shift changes what matters in the estimate. On a unit price bid, quantity takeoff still matters (it tells you how to spread fixed costs), but the real work is building a unit cost you can actually hit.
How do you build a unit price?
A unit price has to cover everything it takes to put one unit in place, plus its share of costs that don't scale with quantity:
- Direct cost per unit: labor, equipment and material for one unit, based on realistic production rates.
- Fixed costs spread across the estimated quantity: mobilization, setup, supervision and equipment that sits on the job regardless of how many units you install. If there is no separate mobilization item, these costs live inside the unit prices.
- Overhead and profit: your markup, applied the way the bid form allows.
The spread of fixed costs is where unit price jobs go wrong. If you spread $40,000 of setup across 2,000 estimated units, each unit carries $20. Install only 1,200 units and you recover $24,000 of that $40,000. Install 3,000 and you over-recover. That is exactly the problem quantity variation clauses are written to fix.
What happens when actual quantities overrun or underrun?
Most public unit price contracts include a variation in estimated quantity clause. It lets either party reprice a unit item when the actual quantity moves far enough from the estimate.
The federal version is FAR 52.211-18. If the actual quantity of a unit-priced item varies more than 15 percent above or below the estimated quantity, either party can demand an equitable adjustment. The adjustment is based only on the change in costs caused by the variation above 115 percent or below 85 percent of the estimate. If the variation delays completion, the contractor can request a time extension in writing within 10 days from the beginning of the delay.
State highway departments write their own versions. A Roads & Bridges column on these clauses notes the threshold is typically between 15 and 25 percent, and some clauses treat major and minor bid items differently.
Three points GCs miss:
- The clause only adjusts for cost changes caused by the quantity change. You have to show how your cost per unit actually moved, for example fixed costs over- or under-recovered, or a different production method at a larger scale.
- It is not the only clause that applies. The same Roads & Bridges column points out that when extra quantities come from a change in the work, pricing falls under the changes clause, not the quantity variation clause. Don't let a quantity variation clause cap a claim that is really a differing site condition or a design change.
- Read the measurement and payment section. Some contracts include allowances or "no separate payment" language that limits what is paid per unit, so the installed quantity and the paid quantity can differ. Know that before you bid.
What is an unbalanced bid?
An unbalanced bid loads extra price onto some unit items and less onto others, usually betting that certain quantities will overrun. Owners watch for it. The Washington State Auditor's Office, in its change order best practices for public owners, warns them to watch line-item pricing for unbalanced bids, since a contractor can have the lowest total and still charge higher prices on some items.
Front-loading early items or betting on a quantity overrun can get a bid rejected on public work and damage trust with a private owner. The safer approach is to price each item at its real cost and spread fixed costs honestly.
How do you bill a unit price contract?
Billing is where unit price margin quietly leaks. Each period you bill quantity installed to date times the unit price, usually against a schedule of values that lists each bid item. See how to set up a schedule of values and progress billing in construction.
To bill measured work cleanly:
- Agree quantities in the field. Get the inspector or owner's rep to confirm measured quantities as work is installed, not weeks later.
- Tie daily reports to bid items. Log quantities against the bid item number every day, so the billing quantity comes from the field record, not a month-end guess.
- Reconcile installed vs billed each period. Any installed quantity not yet billed, or billed but not yet accepted, should show on a list someone owns.
- Watch items near the variation threshold. When an item is trending past 115 or 85 percent of the estimate, flag it early and send written notice.
How do unit prices work in change orders?
Unit prices are also a fast way to price changes. Many owners and GCs ask subs for add and deduct unit prices during buyout, so extra quantities can be priced without a fresh negotiation. The Washington State Auditor's Office lists unit pricing from the original contract as one basis for pricing change orders, while warning it may not fit when the work is different, prices are out of date or quantities change significantly.
Before you accept a sub's unit prices for adds, check that they were not trimmed to win the bid. Then track every unit price change in the change order log with the measured quantity as backup.
This article is general information, not legal advice. Unit price and quantity variation rules depend on your contract and jurisdiction, so check your contract with a construction attorney.
FAQ
What is a unit price contract in construction?
A unit price contract pays the contractor a fixed price per unit of work installed, such as per cubic yard, linear foot or ton. The bid quantities are estimates, and payment is based on measured quantities.
Who carries the risk in a unit price contract?
The owner carries most of the quantity risk, because it pays for actual measured quantities. The contractor carries the cost risk per unit, so a unit price that is too low loses money on every unit installed.
What happens if quantities overrun on a unit price contract?
It depends on the contract. Under the federal clause FAR 52.211-18, either party can demand an equitable adjustment for the part of a quantity variation above 115 percent or below 85 percent of the estimate. State and private contracts set their own thresholds.
How do you bill a unit price contract?
Each billing period, multiply the quantity installed and accepted to date by the unit price for each bid item. Keep field-confirmed quantities as backup and reconcile installed quantities against billed quantities every period.
Keep the unit price and the field quantity on one record
Unit price margin depends on the estimate, the daily quantities and the bill all agreeing. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate becomes the live project, and subcontracts, change orders, pay apps, payments and the general ledger hang off the same deliverables. It has built-in accounting (GL, AP and AR), connects to QuickBooks Online, and takes payments through Stripe. Stop stacking Procore, QuickBooks and a spreadsheet to figure out what you installed and what you billed.