Performance Bond Claim: How GCs Call a Subcontractor's Bond

A performance bond claim, step by step for GCs: notice, default and termination, what the surety asks for, its options, and mistakes that void claims.

Published
Reading time
6 min read
Author
Adam HicksFounder, CooperBuild AI
On this page9 sections
  1. How does a performance bond claim work?
  2. What should you do before you call the bond?
  3. How do you declare a subcontractor in default?
  4. What will the surety ask you for?
  5. What options does the surety have?
  6. How long does a surety take to respond?
  7. What mistakes cost GCs their bond claim?
  8. FAQ
  9. What is a performance bond claim?
  10. Do you have to terminate a subcontractor before making a performance bond claim?
  11. How long does a surety have to respond to a performance bond claim?
  12. What is the difference between a performance bond claim and a payment bond claim?
  13. Keep the paper trail on the job record

By Adam Hicks, CooperBuild AI · November 26, 2026

A performance bond claim is how a general contractor asks a subcontractor's surety to step in after the sub defaults. To make one stick, you usually have to follow the bond's own steps in order: warn the sub and the surety, formally declare the default in writing, terminate the subcontract where the bond requires it, and keep the remaining subcontract balance available for completion. Skip a step and the surety may have a defense.

This guide covers the process from the GC's side: what the bond requires, what the surety will ask for, what it can do, and the mistakes that cost GCs their claim.

How does a performance bond claim work?

A performance bond is a three-party agreement. On a subcontract bond, the subcontractor is the principal, the surety guarantees its performance, and you, the GC, are the obligee. The surety is secondarily liable: the sub stays primarily responsible for its work and must reimburse the surety for any loss (AGC, The Contract Surety Bond Claims Process (opens in a new tab)).

So a bond claim isn't an insurance claim. The surety investigates whether the sub really defaulted and whether you held up your end of the subcontract.

Many performance bonds require three conditions before the surety must act: the sub is in default, you have declared it in default, and you have performed your own obligations (Travelers (opens in a new tab)). Some bond forms add more.

What should you do before you call the bond?

Start well before the default letter.

  1. Pull the bond and the subcontract. Read the bond's notice, default and termination conditions and the subcontract's cure clause. As one commenter put it on r/Construction, the bond itself will say how to serve notice and claim against it (r/Construction (opens in a new tab)).
  2. Confirm the surety is real and reachable. Get the surety's claim contact from the bond or the surety's website. For federal work, the Treasury's Circular 570 (opens in a new tab) lists approved sureties and their contact details. NASBP suggests GCs identify the surety early and consider legal counsel to prepare a documented written claim notice (NASBP (opens in a new tab)).
  3. Send a notice to cure under the subcontract. Be specific about what is late or defective and the deadline. See our notice to cure guide.
  4. Bring the surety in early. The AGC guide says early communication "vastly improves" the claims process, and that a meeting of the GC, the sub and the surety is almost always useful even when the bond doesn't require one. Some bonds do require that meeting before you can declare a default.

Sureties generally have no duty to act before a default is declared (Construction Risk (opens in a new tab)), but one that already knows the job can move faster once you do.

How do you declare a subcontractor in default?

In writing, and in the way the bond and subcontract say.

The letter should identify the subcontract and bond, cite the clauses breached, lay out what happened with dates, reference your cure notice, and state clearly that you are declaring the sub in default. Send it to the sub and the surety at the notice addresses in the documents.

Then check whether the bond requires termination. Two contractors can't perform the same work at the same time, which is one reason most bond forms make formal termination of the bonded contract a condition before the surety has to perform (AGC). A default declaration without a termination may not trigger the surety's obligations under those forms.

A wrongful default termination can leave you liable to the sub, so talk to a construction attorney first. And don't reach for a termination for convenience clause instead; that usually isn't a default at all.

What will the surety ask you for?

The investigation asks two questions: did the sub default, and did you perform? Have these ready:

  • The executed subcontract, bond, and all change orders
  • The schedule, and updates showing where the sub fell behind
  • Daily reports, photos and inspection reports showing the defective or missing work
  • Notices to cure, default and termination letters, and the sub's responses
  • Pay applications, the payment history with dates, and a reconciliation of the subcontract balance
  • Backcharges and the costs you've already spent fixing the problem
  • Any claims or notices you've received from the sub's own suppliers and lower-tier subs

If you paid late, slowed the sub with late approvals, or spent the balance, expect the surety to raise it.

What options does the surety have?

The bond may list the options, or may be silent. The AGC guide describes the common ones:

  • Finance the sub. If the sub is competent but out of cash, the surety may fund completion by the original sub. You may be asked to pay through joint checks so contract funds stay on the job. Our joint check agreement guide covers how those work.
  • Tender a replacement. The surety and the GC agree on a new subcontractor, and the surety funds any cost above the remaining subcontract balance.
  • Take over. The surety takes responsibility for completing the work itself, usually with a completion contractor, often under a written takeover agreement.
  • Let the GC complete. The surety stays out of the completion and remains exposed for the cost above the remaining balance, up to the bond's penal sum. Sureties usually choose this only when the work is close to done and your completion plan is reasonable.
  • Deny the claim. If the surety concludes it has no liability under the bond, it can decline to perform.

Cash settlements and other combinations are possible too. Check the bond's penal sum against your exposure.

How long does a surety take to respond?

Many bond forms say only that the surety must act "promptly" once its obligations are triggered. In practice, Travelers notes that an investigation can take weeks to several months, and under many forms the sub's scope sits idle while you wait. If that scope is on the critical path, a long investigation can hurt your whole schedule.

The bond protects your money, not your schedule. Plan for the delay, track its cost, and keep the owner informed with a proper delay notice.

What mistakes cost GCs their bond claim?

  • Missing notice conditions. Claimants must comply strictly with the bond's notice provisions and time limits (Construction Risk). Read them first, not after the dispute.
  • Finishing the work before telling the surety. Skipping the bond's notice steps can prejudice the surety's right to limit its loss and may release it (MWH Law Group (opens in a new tab)). One appellate case let a GC recover without notice only because that bond had no notice requirement (Construction Risk).
  • Paying out the balance. Paying the defaulting sub ahead of its work, or spending the remaining balance on other things, weakens the claim.
  • Thin records. A default you can't show with dated reports, photos and letters is just a dispute.
  • Waiting too long. The AGC guide notes that obligees are often slow to declare a default and tolerate poor performance for long stretches while the sub promises to improve.

This article is general information, not legal advice. Bond terms, state law and court decisions vary, and some deadlines are strict, so confirm the steps for your bond with a construction attorney and your surety bond producer.

FAQ

What is a performance bond claim?

A performance bond claim is a demand by the obligee, such as a GC on a subcontract bond, asking the surety to remedy the principal's default. The surety investigates and then finances, replaces, takes over, pays or denies.

Do you have to terminate a subcontractor before making a performance bond claim?

Often, yes. Most bond forms make formal termination of the bonded contract a condition before the surety must perform, though the exact steps depend on your bond. Read it and get legal advice first.

How long does a surety have to respond to a performance bond claim?

Many bonds only require the surety to act promptly once its obligations are triggered. Investigations can take weeks to several months, so plan your schedule around that possibility.

What is the difference between a performance bond claim and a payment bond claim?

A performance bond claim is made by the obligee when the principal fails to perform the work. A payment bond claim is made by unpaid lower-tier subs and suppliers against a payment bond.

Keep the paper trail on the job record

A bond claim is won or lost on records. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate becomes the live project, and subcontracts, pay apps, payments and the general ledger hang off the same deliverables. It has built-in accounting (GL, AP and AR), connects to QuickBooks Online, and takes payments through Stripe. Stop stacking Procore, QuickBooks and a spreadsheet to rebuild a sub's history when a default hits.

If you want every sub's paper trail on one record, start a 14-day free trial (opens in a new tab).

Written by

Adam Hicks, Founder, CooperBuild AI

Get started

Run your next job in Cooper.

Start on free credit and run a real job this week, or book a 30-minute demo on your own spec set, estimate or card statement. Either way, no card and no contract.

$20 in free credits, no card needed