  1. What is a payment bond claim?
  2. When does the Miller Act require a payment bond?
  3. Who can file a Miller Act payment bond claim?
  4. What are the Miller Act payment bond claim deadlines?
  5. How do Little Miller Act claims differ by state?
  6. What should a GC do when a payment bond claim arrives?
  7. How can a GC prevent payment bond claims?
  8. Where CooperBuild AI fits
  9. FAQ
  10. What is a payment bond claim?
  11. How long do you have to file a Miller Act payment bond claim?
  12. Can a third-tier subcontractor make a Miller Act claim?
  13. Does a GC have to tell its surety about a payment bond claim?

By Adam Hicks, CooperBuild AI · November 23, 2026

A payment bond claim is how an unpaid subcontractor or supplier on a bonded public job gets paid when it can't file a mechanics' lien. Instead of liening the property, the claimant sends written notice and, if needed, sues on the prime contractor's payment bond. The rules are strict: on federal work the Miller Act sets 90-day and one-year deadlines, and each state's "Little Miller Act" has its own notice steps.

This guide is written for general contractors on both sides of the claim: when your own subs and suppliers might claim against your bond, and when you need to protect your rights on someone else's.

What is a payment bond claim?

A payment bond is a surety's promise, posted by the prime contractor, that people who furnish labor and material on the project will be paid. Public property generally can't be liened, so on public work the bond replaces the lien as the payment remedy for lower tiers.

A payment bond claim is the formal demand on that bond. It usually starts with a written notice and ends, if the debt stays unpaid, with a lawsuit against the prime contractor and its surety.

When does the Miller Act require a payment bond?

The federal Miller Act (40 U.S.C. §§ 3131–3134) applies to federal construction contracts. Under FAR 28.102-1 (opens in a new tab), performance and payment bonds are required for any construction contract exceeding $150,000. For contracts over $35,000 up to $150,000, the contracting officer picks two or more alternative payment protections, such as a payment bond or an irrevocable letter of credit.

Older guides still quote a $100,000 threshold, so check the current FAR rather than a dated brochure. The Miller Act doesn't cover state or local public work; that is what the state Little Miller Acts are for (ABA (opens in a new tab)).

Who can file a Miller Act payment bond claim?

The Miller Act protects two tiers below the prime (ABA (opens in a new tab)):

  • First-tier subcontractors and suppliers with a direct contract with the prime.
  • Second-tier subcontractors and suppliers with a direct contract with a first-tier subcontractor.

It does not protect a supplier to a supplier, or anyone at the third tier and below. Design professionals hired by the prime or a first-tier sub generally aren't covered either. As a GC, this tells you whose nonpayment can turn into a claim against your bond.

What are the Miller Act payment bond claim deadlines?

The deadlines are in 40 U.S.C. § 3133 (opens in a new tab):

  • 90-day notice (second tier only): a claimant without a contract with the prime must give the prime written notice within 90 days of its last labor or material. The notice must state the amount with substantial accuracy and name the party it furnished to, and be served by a method with third-party verification of delivery.
  • 90-day wait: any claimant may sue once it hasn't been paid in full 90 days after its last labor or material.
  • One-year suit deadline: the suit must be brought within one year after the claimant's last labor or material.

The suit is filed in the name of the United States, for the use of the claimant, in the federal district court where the contract was performed. First-tier claimants don't need to send the 90-day notice, but sending a clear written demand is still good practice.

How do Little Miller Act claims differ by state?

State bond statutes share the idea but differ on thresholds, notice timing and who gets notice. Two examples show how much they vary:

  • Texas (Gov't Code ch. 2253): a payment bond is required on public work contracts over $25,000, or over $50,000 for municipalities. Claimants must mail notice to the prime contractor and the surety by the 15th day of the third month after each month the claimed work or material was furnished, with a sworn statement of account (§ 2253.041 (opens in a new tab)). Second-tier claimants also owe the prime an earlier second-month notice (§ 2253.047 (opens in a new tab)). Suit is due within a year of the date the notice was mailed (§ 2253.078 (opens in a new tab)).
  • Florida (§ 255.05 (opens in a new tab)): a claimant not in privity with the contractor (other than a laborer) must serve a notice that it intends to look to the bond within 45 days of starting work. A sworn notice of nonpayment then goes to the contractor, with a copy to the surety, no earlier than 45 days after first furnishing and no later than 90 days after final furnishing. Suit is generally due within one year.

Notice the Texas clock runs month by month, not from the last day on the job. A sub that waits for the end of a long project can lose the right to claim early months. Always read the statute for the state and owner on your job.

What should a GC do when a payment bond claim arrives?

Treat it as urgent, even if you think the claim is wrong. A practical sequence:

  1. Forward it to your surety and bond producer the same day. Your bond and indemnity agreement usually require prompt notice, and the surety will want your position.
  2. Check timeliness and content. Is the claimant in a covered tier? Was notice served on time, by the required method, with the required details? Late or defective notice can be a defense.
  3. Pull the paper trail. Compare the claim with the sub's subcontract, approved pay apps, change orders, backcharges and what you've already paid. Our subcontractor pay application review guide covers what to check.
  4. Protect the money still in your hands. Talk to your attorney about holding funds from the first-tier sub's next payment and paying the claimant directly or by joint check.
  5. Collect releases when you pay. Get a written release from the claimant for the amount settled so it isn't claimed twice. See conditional vs. unconditional lien waivers for how waiver wording works.

Most claims come from a first-tier sub that has stopped paying its own suppliers. That's a default warning sign, so review your subcontractor default insurance vs. bonds options and your plan for the rest of that scope.

How can a GC prevent payment bond claims?

Prevention is mostly visibility. Know who is working under each sub before they arrive, and track what you've paid against every subcontract and change order.

  • Ask subs to list their second-tier subs and major suppliers at buyout.
  • Pay on time under your contract and the applicable prompt payment act, so your subs can pay theirs.
  • Collect releases from lower tiers with each payment on public jobs.
  • Watch for early signals: late paperwork, suppliers calling you directly, or a sub asking for advances.

One more rule worth knowing: under § 3133(c), a waiver of the right to sue on a Miller Act payment bond is void unless it is in writing, signed by the claimant, and executed after the claimant has furnished labor or material. A waiver buried in a subcontract signed before work starts won't hold up.

Where CooperBuild AI fits

Answering a bond claim quickly depends on seeing every subcontract, change order, pay app and payment for the job in one place. CooperBuild AI is an AI-native operating system for general contractors. The estimate becomes the live project, and commitments, vendor bills, pay apps and job costs hang off the same line items. It includes built-in accounting (GL, AP and AR), connects to QuickBooks Online and supports integrated payments through Stripe.

If you want that view of your subs and payments on every job, start a 14-day free trial (opens in a new tab).

FAQ

What is a payment bond claim?

A payment bond claim is a demand by an unpaid subcontractor, supplier or laborer against the payment bond posted by the prime contractor on a bonded project, usually public work. It starts with any required written notice and can lead to a lawsuit against the prime contractor and the surety.

How long do you have to file a Miller Act payment bond claim?

A second-tier claimant must give the prime contractor written notice within 90 days of its last labor or material. Any claimant may sue once 90 days pass without full payment, and the suit must be filed within one year after the claimant's last labor or material.

Can a third-tier subcontractor make a Miller Act claim?

No. The Miller Act covers subcontractors and suppliers with a direct contract with the prime contractor or with a first-tier subcontractor. Third-tier claimants and suppliers to suppliers are not covered, although some state statutes reach further.

Does a GC have to tell its surety about a payment bond claim?

Your bond and indemnity agreement almost always require prompt notice to the surety, and the surety will rely on your records to respond. Even where a statute doesn't require the claimant to notify the surety, forward any claim you receive right away.

This article is general information, not legal advice. Payment bond statutes, thresholds and deadlines vary by jurisdiction and change over time, and courts apply them strictly; confirm the rules for your project with a construction attorney.

Written by

Adam Hicks, Founder, CooperBuild AI

Get started

Run your next job in Cooper.

Start on free credit and run a real job this week, or book a 30-minute demo on your own spec set, estimate or card statement. Either way, no card and no contract.

$20 in free credits, no card needed