Prompt Payment Act in Construction: Deadlines by State

How the prompt payment act works in construction: federal 14- and 7-day rules, NY, CA and TX deadlines, interest on late pay and what stops the clock.

Published
Reading time
7 min read
Author
Adam Hicks
On this page8 sections
  1. What is a prompt payment act in construction?
  2. How does the federal Prompt Payment Act work on construction jobs?
  3. What are prompt payment deadlines by state?
  4. What stops the prompt payment clock?
  5. Do prompt payment laws override pay-when-paid clauses?
  6. How can GCs and subs use prompt payment rules?
  7. FAQ
  8. What is the Prompt Payment Act in construction?
  9. How many days does a general contractor have to pay a subcontractor?
  10. How long does an owner have to pay a contractor?
  11. What interest is owed on late construction payments?
  12. Can an owner or GC withhold payment under prompt payment laws?
  13. Track pay app dates in one place

By Adam Hicks, CooperBuild AI · November 14, 2026

A prompt payment act in construction is a law that sets deadlines for paying contractors and subcontractors and charges interest when payment is late. On federal jobs, the government generally pays progress payments 14 days after it receives a proper request, and the prime must pay its subs within 7 days of being paid. State laws set their own clocks, and the deadlines, interest rates and covered projects differ by state.

If you bill monthly, these laws decide when late money starts costing the other side. This guide covers the federal rules, how three large states handle private work, what usually stops the clock and how GCs and subs can use the rules without starting a fight. It is general information, not legal advice; read your contract and the statute for your job, and talk to a construction attorney before you rely on either.

What is a prompt payment act in construction?

Prompt payment laws do three things. They set a deadline for the owner to pay the contractor after a proper payment request, set a shorter deadline for each tier to pass money down to its subs and suppliers, and add interest or a penalty when a payment is late without a valid reason.

They don't make the owner pay for work that wasn't done or wasn't documented. Most allow withholding for a good faith dispute, defective work or missing contract paperwork. The point is that money that is actually owed can't sit in someone's bank account indefinitely.

How does the federal Prompt Payment Act work on construction jobs?

On federal construction contracts, the FAR prompt payment clause makes progress payments due 14 days after the designated billing office receives a proper payment request. Final payment is due the later of 30 days after a proper invoice or 30 days after the government accepts the work (FAR 52.232-27 (opens in a new tab)).

The law also reaches down the chain. Each federal construction contract must require the prime to pay subs and suppliers for satisfactory work within 7 days of being paid by the agency, with an interest penalty if it doesn't, and the same clause must flow to every lower tier (31 U.S.C. § 3905 (opens in a new tab)).

A prime can still withhold, but only by the subcontract's terms and with a written notice to the sub stating the amount withheld, the reason and what the sub has to do to get paid, with a copy to the government. Disputes between a prime and its sub are not disputes the United States is party to. Interest is figured at the Treasury's prompt payment rate, which is 4.75% for July 1 to December 31, 2026 (Bureau of the Fiscal Service (opens in a new tab)).

What are prompt payment deadlines by state?

Every state sets its own rules. Here is how three large states handle private commercial work:

State Owner pays GC GC pays subs Late payment charge
New York (private jobs over $150,000) Approve or reject within 12 business days; pay within 30 days of approval Within 7 days of receiving payment 1% per month
California (private works) Within 30 days of a payment demand, unless agreed otherwise in writing Within 7 days of receiving a progress payment, unless agreed otherwise in writing 2% per month
Texas (private owners) Within 35 days of a written payment request Within 7 days of receiving payment 1.5% per month

New York. The Prompt Payment Act covers private construction contracts over $150,000. Once the owner has the invoice and all contractually required documentation, it has 12 business days to approve or disapprove, and any disapproval needs a written statement of the items not approved. Payment is due 30 days after approval, and contractors and subs pay the next tier within 7 days of receipt (N.Y. Gen. Bus. Law § 756-a (opens in a new tab)). Late payments carry interest of 1% per month, and a contractor that isn't paid on an approved invoice may suspend work after 10 days' written notice (Bialkowski Law summary (opens in a new tab)).

California. On private works, the owner pays progress payments that aren't in good faith dispute within 30 days after a payment demand, may withhold no more than 150% of a disputed amount and owes 2% per month on amounts wrongfully withheld (Cal. Civ. Code § 8800 (opens in a new tab)). Contractors pay subs within 7 days of each progress payment, with the same 150% dispute cap and a 2% per month penalty, on both private and most public works (Cal. Bus. & Prof. Code § 7108.5 (opens in a new tab)).

Texas. Private owners pay within 35 days of a written payment request for properly performed work or suitably stored or specially fabricated materials. Each tier pays the next within 7 days of receiving payment, unpaid amounts accrue 1.5% interest per month and attempts to waive the chapter are generally void (Tex. Prop. Code ch. 28 (opens in a new tab)). The owner's deadline shifts when a lender fails to fund.

Public owners in each state usually follow separate public contracting rules, so check which statute applies before you count days.

What stops the prompt payment clock?

Most prompt payment laws only start the clock on a proper request. That usually means the right billing period, the agreed format, the backup the contract requires and any waivers or certificates that must come with it. Common reasons a payment can be held without breaking the law:

  • A good faith dispute over the amount or the quality of the work.
  • Defective work that hasn't been fixed.
  • Missing required documents, such as insurance certificates or backup for stored materials.
  • Retainage the contract allows the owner to hold. See retainage in construction.

The statutes above also limit how far a dispute can reach. California caps withholding at 150% of the disputed amount, and New York requires a written statement of what was not approved.

Do prompt payment laws override pay-when-paid clauses?

Not always, and the answer depends on the state. The subcontractor deadlines above run from when the GC receives payment, so they work alongside a pay-when-paid clause rather than replacing it. Some states go further and limit or void pay-if-paid clauses. Read pay-when-paid vs pay-if-paid for how courts treat each clause, and check your state's rules before you sign a subcontract.

How can GCs and subs use prompt payment rules?

For subs, the practical moves are simple. Track when you sent each complete pay application, when the GC was paid and when your payment arrived. Ask the GC when the owner paid, in writing. If the payment is late, send a short written notice citing the contract and the statute before you escalate. Interest only helps if you can prove the dates.

For GCs, the same rules protect you upstream. Submit clean, complete pay apps on the agreed date so the owner's clock starts, document every rejection in writing and pay subs within the window once you are funded. If you need to withhold from a sub, send a written notice with the amount, the reason and the fix, as the federal rule requires. Our guide to getting paid faster covers the billing habits that keep money moving.

FAQ

What is the Prompt Payment Act in construction?

It is a law that sets deadlines for paying contractors, subcontractors and suppliers on construction jobs and adds interest when payment is late. There is a federal act for government contracts, and states have their own prompt payment statutes.

How many days does a general contractor have to pay a subcontractor?

On federal jobs, 7 days after the prime is paid. New York, California and Texas also use 7 days after receipt of payment for private work, but deadlines vary by state and by contract, so check the statute that applies to your job.

How long does an owner have to pay a contractor?

It depends on the law that applies. Federal progress payments are generally due 14 days after a proper request. In New York the owner has 12 business days to approve and 30 days after approval to pay, California allows 30 days after a payment demand and Texas allows 35 days after a written request.

What interest is owed on late construction payments?

It varies. The federal rate is 4.75% for July to December 2026. New York charges 1% per month, California 2% per month and Texas 1.5% per month on amounts paid late.

Can an owner or GC withhold payment under prompt payment laws?

Yes, for valid reasons such as a good faith dispute, defective work or missing contract documents. Many statutes require a written explanation, and some cap how much can be held for a dispute.

Track pay app dates in one place

Prompt payment rights depend on proving dates: when the pay app went out, when it was approved, when the money came in and when subs were paid. CooperBuild AI keeps project chat, tasks and job records together, so billing questions and action items stay attached to the job, and its assistants can pick up follow-ups from the team's conversation. It includes accounting with GL, AP and AR, connects to QuickBooks Online and supports integrated payments through Stripe.

Get started with a free trial of CooperBuild AI and keep every pay app date where your team can find it.

Written by

Adam Hicks

Get started

Run your next job in Cooper.

Start on free credit and run a real job this week, or book a 30-minute demo on your own spec set, estimate or card statement. Either way, no card and no contract.

$20 in free credits, no card needed