Construction Draw Schedule: A GC's Guide to Lender Draws

A construction draw schedule sets when a lender releases loan money to the GC. How draws, inspections and retainage work, and how to stop floating it.

Published
Reading time
7 min read
Author
Adam HicksFounder, CooperBuild AI
On this page8 sections
  1. What is a construction draw schedule?
  2. How does the construction draw process work?
  3. Why do GCs end up floating the job between draws?
  4. How do you build a draw schedule that doesn't starve the job?
  5. Match the draw schedule to the schedule of values
  6. Negotiate deposits and stored materials up front
  7. Agree on the draw calendar
  8. Align sub payment terms with the draw cycle
  9. What documents does a lender want with each draw?
  10. How do you keep the draw from coming back short?
  11. Where CooperBuild AI fits
  12. FAQ
  13. What is a construction draw schedule?
  14. How long does a construction draw take to fund?
  15. Can a lender pay for materials before they are installed?
  16. Who pays subcontractors when the work is funded by a construction loan?

By Adam Hicks, CooperBuild AI · November 22, 2026

A construction draw schedule is the agreed plan for when a construction lender releases loan money to pay for the work, usually monthly or at set milestones, and only after the work (or stored material) is verified. For a general contractor, it decides how long you float labor, subs and materials before cash arrives. Build your billing, sub payment terms and cash forecast around it before the job starts, not after the first draw comes back short.

What is a construction draw schedule?

When an owner finances a project with a construction loan, the bank does not hand over the full loan at closing. It disburses the money in pieces, called draws, as the job progresses. The draw schedule is the document, usually attached to the loan agreement or the owner-GC contract, that spells out how those pieces are released.

There are two common shapes:

  • Milestone (stage) draws. A fixed percentage of the loan is released when a defined stage is done: foundation, framing, dry-in, rough-ins, drywall, final. This is most common on residential and small custom builds.
  • Monthly progress draws. The GC submits a pay application each month against a schedule of values, showing percent complete by line item. The lender's inspector checks the work in place, and the bank funds the verified amount less retainage. This is the norm on commercial work.

Either way, the core rule is the same: lenders pay in arrears for verified work. The OCC's Comptroller's Handbook on commercial real estate lending tells banks to make sure "construction draws are commensurate with verified improvements and that the budget remains in balance with sufficient funds available to fund completion." That one sentence explains most of the friction GCs feel with draws.

How does the construction draw process work?

A typical monthly draw cycle looks like this:

  1. The GC prepares the pay application. Percent complete by schedule of values line, stored materials, approved change orders, retainage held, and the net amount due.
  2. Backup goes with it. Lenders commonly ask for sub and supplier invoices, lien waivers from the GC and lower tiers, updated budget and schedule, and proof of insurance for stored materials. The exact list lives in the loan agreement and the lender's disbursement instructions.
  3. The owner (and often the architect) reviews it. On many jobs the owner signs off before it goes to the bank.
  4. The lender's inspector visits. An independent inspector or construction consultant confirms the claimed progress. The OCC handbook says banks should require architect or engineering inspection reports "independent of the borrower" with each draw.
  5. The title company updates coverage. On many commercial loans the title insurer runs a date-down search for new liens and issues a disbursement endorsement (such as ALTA 33) before money moves.
  6. The bank funds. Money goes to the owner, the GC directly, or a title or escrow agent who pays out.

Every one of those steps can add days. That is why the draw schedule matters as much as the contract price.

Why do GCs end up floating the job between draws?

Because the lender pays after the work is verified, and your crews, subs and suppliers want to be paid as the work happens. GCs discuss this constantly. In an r/Homebuilding thread on a bank that would only fund each draw after work was complete, the top replies called it normal, and one builder described a $280k special-order window package that had to be paid up front but wasn't funded until it was installed, inspected weeks later, and then paid two weeks after that. In r/Contractor, a builder weighing two bank-financed jobs worth about $500k asked whether it was even worth it, and the replies pointed to the 10% holdback that forces the GC to float part of every draw.

The gap comes from a few predictable places:

  • Arrears billing. You bill for last month's work, then wait for review, inspection and funding.
  • Retainage. The lender or owner holds back a percentage of each draw until completion. See our guide to retainage in construction.
  • Long-lead and deposit-heavy items. Equipment, windows and specialty materials often need deposits long before they're "in place."
  • Rejected or reduced line items. If the inspector sees 40% where you billed 60%, you get 40%.

How do you build a draw schedule that doesn't starve the job?

You often can't change the lender's rules, but you can shape the schedule before the contract is signed.

Match the draw schedule to the schedule of values

If you bill monthly, your schedule of values is the draw schedule's backbone. Break it into lines an inspector can actually verify on a site walk. "Electrical: 100%" invites arguments; "electrical rough-in, level 2" doesn't. Front-loading the SOV to pull cash early is tempting, but lenders and their inspectors watch for it, and it can cost you credibility on every later draw.

Negotiate deposits and stored materials up front

If the job has deposit-heavy items, get them written into the draw schedule as their own line or milestone, with the documentation the lender wants for stored materials (invoices, bill of sale, insurance, photos, and for off-site storage, bonded or insured storage). Our guide to stored materials billing covers what lenders and owners usually ask for.

Agree on the draw calendar

Pin down the dates: when the pay app is due, when the inspector visits, and when funding is expected. If the lender needs your package by the 25th to fund by the 10th, line your sub billing cutoff up with that date so you aren't paying subs on the 1st for money that arrives on the 15th.

Align sub payment terms with the draw cycle

Many GCs on loan-funded work set sub terms so subs are paid after the GC receives the corresponding draw. Be careful: whether a pay-when-paid or pay-if-paid clause holds up depends on contract wording and state law, and prompt payment statutes can set deadlines once you're paid. Read our explainers on pay-when-paid vs pay-if-paid and the Prompt Payment Act before you rely on either.

What documents does a lender want with each draw?

It varies by lender and loan, so always work from the disbursement instructions. Commonly requested items include:

  • The pay application and continuation sheet, tied to the approved schedule of values
  • Approved change orders, plus an updated budget showing the loan is still "in balance"
  • Conditional lien waivers for the current draw and unconditional waivers for the previous one, from the GC and listed subs and suppliers (see conditional vs unconditional lien waivers)
  • Sub and supplier invoices
  • Stored materials documentation
  • An updated schedule or progress photos

Missing one waiver from one supplier can hold the whole draw, so collect lower-tier paperwork on the same cutoff as their invoices.

How do you keep the draw from coming back short?

  • Walk the job before you bill. Bill what an outsider would see. If it isn't visibly in place, expect it to be cut.
  • Keep change orders current. Unapproved change work usually can't go on the draw. Get it signed before cutoff.
  • Reconcile the budget every month. Lenders check that remaining loan funds plus owner equity cover the cost to finish. If your committed costs say otherwise, raise it early.
  • Forecast the float. Put draw dates, retainage and sub payment dates in a simple construction cash flow forecast so you know your low point before you hit it.

Where CooperBuild AI fits

Draws go wrong when the estimate, the schedule of values, change orders, sub invoices and the books live in different places, so every pay app gets rebuilt by hand. CooperBuild AI is an operating system for general contractors where the approved estimate becomes the live project, and the schedule of values, pay applications, vendor bills and job costs hang off the same line items. It includes built-in accounting (GL, AP and AR), connects to QuickBooks Online, and supports integrated payments through Stripe. Because pay apps, vendor bills and job costs share the same data, you can see where every line stands before the draw goes out.

If your next job is loan-funded, start a free trial or book a 20-minute working session on your last bid and see how the draw would have looked.

FAQ

What is a construction draw schedule?

A construction draw schedule is the plan for when a construction lender releases loan funds during a project, either at set milestones or monthly based on verified percent complete, usually less retainage.

How long does a construction draw take to fund?

It depends on the lender, the loan agreement and how complete your package is. The cycle includes owner review, an inspector's site visit and often a title date-down, so build several days to a few weeks into your cash forecast and confirm the lender's calendar before the job starts.

Can a lender pay for materials before they are installed?

Sometimes. Many loan agreements allow stored materials to be funded if you provide invoices, proof of ownership, insurance and, for off-site storage, secure or bonded storage. Get it written into the draw schedule up front.

Who pays subcontractors when the work is funded by a construction loan?

The GC pays its subcontractors under the subcontract terms. The lender funds the owner or GC draw, and many GCs set sub terms to line up with that draw cycle, subject to state prompt payment laws.

This article is general information, not legal or financial advice. Loan terms, lien law and prompt payment rules vary by lender and state.

Written by

Adam Hicks, Founder, CooperBuild AI