Differing Site Conditions: How GCs Handle Type I and II

Differing site conditions explained for GCs: Type I vs Type II, what you must prove, how to give notice and how to price the change order.

Published
Reading time
6 min read
Author
Adam Hicks
On this page10 sections
  1. What are differing site conditions in construction?
  2. What is the difference between a Type I and Type II condition?
  3. What do you have to prove in a differing site conditions claim?
  4. Does a site investigation clause kill your claim?
  5. How do you give notice of a differing site condition?
  6. What should you document on site?
  7. How do you price a differing site conditions change order?
  8. How do GCs handle differing site conditions with subs?
  9. FAQ
  10. What are differing site conditions?
  11. What is a Type 1 differing site condition?
  12. What is a Type 2 differing site condition?
  13. How soon must you give notice of differing site conditions?
  14. Can you claim differing site conditions without a clause in the contract?
  15. Keep site conditions tied to the job

By Adam Hicks, CooperBuild AI · November 15, 2026

Differing site conditions are physical conditions at the site that turn out to be materially different from what the contract documents showed, or unusual conditions nobody would normally expect for that kind of work. When the contract has a differing site conditions clause and you give timely written notice, you can usually ask for more money, more time or both. Without notice and documentation, most of those claims fail.

This guide covers the two types, what you have to prove, how to give notice before the conditions are disturbed and how to price and track the change. It is general information, not legal advice; have a construction attorney review your contract and any claim.

What are differing site conditions in construction?

The federal clause is the model most contracts follow. Under FAR 52.236-2 (opens in a new tab), a contractor must give written notice of two kinds of conditions:

  • Type I: subsurface or latent physical conditions at the site that differ materially from those indicated in the contract.
  • Type II: unknown physical conditions at the site, of an unusual nature, that differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

Federal-aid highway contracts use nearly the same language. 23 CFR 635.109 (opens in a new tab) requires a differing site conditions clause in those projects unless state law says otherwise. Private contracts often include a "concealed or unknown conditions" provision that works the same way.

What is the difference between a Type I and Type II condition?

A Type I condition is measured against the contract. The drawings, borings, specs or other documents indicated one thing, and the site showed another. Think of a boring log showing clay where you hit rock, or drawings showing a slab-on-grade where you find an old foundation.

A Type II condition is measured against normal experience. The contract said nothing about it, but the condition is unusual for that type of work. Contractors on Reddit describe examples like hazardous material hidden in an inaccessible ceiling during a renovation, or a landscaper hitting bedrock on a sprinkler job. Type II claims are generally harder because "unusual" is a high bar.

What do you have to prove in a differing site conditions claim?

More than most contractors expect. An ASCE Civil Engineering Source article (opens in a new tab) on a Type I dispute lists four elements the contractor had to show:

  1. The conditions indicated in the contract differed materially from those encountered.
  2. The conditions encountered were reasonably unforeseeable based on all information available at bid time.
  3. The contractor reasonably relied on its reading of the contract documents.
  4. The contractor was damaged by the difference.

In the case the article describes, the board denied the claim. The specs had warned that buried debris might be encountered, pre-bid photos showed timber piles, and the contractor offered no evidence that it reviewed the soil data before bidding. The lesson: your estimating file is part of your claim.

Does a site investigation clause kill your claim?

Not automatically, but it raises the bar. The federal Site Investigation and Conditions Affecting the Work clause (FAR 52.236-3) (opens in a new tab) has the contractor acknowledge it investigated the site and satisfied itself about conditions reasonably ascertainable from an inspection and from the drawings and specs. Private contracts often go further with "verify existing conditions" or "contractor accepts the site as-is" language.

That means a condition you could have seen on a reasonable site visit is hard to claim later. Walk the site, photograph what you see, note what you could not access, and write down which reports you relied on. If an area is inaccessible before bid, say so in your proposal qualifications.

How do you give notice of a differing site condition?

Fast and in writing. FAR 52.236-2 requires written notice "promptly, and before the conditions are disturbed," and says no equitable adjustment is allowed without the required notice unless the contracting officer extends the deadline. It also bars requests made after final payment. Private contracts set their own deadlines, which can be short, so read yours before you need it.

A practical notice sequence:

  • Stop work in the affected area if you can do it safely, so the owner can see the condition before it is disturbed.
  • Send written notice the same day describing what you found, where, and how it differs from the contract documents.
  • Reference the documents you relied on, such as boring logs, drawings, existing-conditions surveys or specs.
  • Request an inspection by the owner, architect or engineer.
  • Reserve your rights to cost and time, even if you do not have numbers yet.

Our guide to the construction delay notice covers notice letters in more detail.

What should you document on site?

Everything the owner's team will ask for later. Take dated photos and video with a scale reference, record locations and depths, keep the daily report entries, and log the crews and equipment standing by or redirected. Our construction daily report guide lists what a good entry includes.

Keep the cost of the affected work separate from the base scope from the first day. A separate cost code or change event for the condition makes it far easier to show damages than reconstructing costs months later.

How do you price a differing site conditions change order?

Treat it like any other change, with better backup. Price the added labor, material, equipment and subcontract costs, plus extended general conditions if the schedule moves, and include markup only as the contract allows. Note that on federal-aid highway contracts, 23 CFR 635.109 says the adjustment excludes anticipated profits.

If the condition affects the critical path, support the time request with a schedule analysis. Our post on time impact analysis explains how. Then submit through your normal change order process with the notice, photos, reports and cost records attached.

How do GCs handle differing site conditions with subs?

Flow the same terms down. If your prime contract has a differing site conditions clause with a notice deadline, your subcontracts should require subs to notify you sooner, so you have time to notify the owner. A sub's notice that arrives after the owner's deadline can leave you holding the cost.

Collect the sub's photos, quantities and costs in the same format you will send upstream, and keep the sub's pricing tied to the owner change request so both close together.

FAQ

What are differing site conditions?

They are physical site conditions that differ materially from what the contract documents indicated (Type I), or unusual conditions that differ materially from those ordinarily encountered in that kind of work (Type II). A differing site conditions clause lets the contractor request a price or time adjustment.

What is a Type 1 differing site condition?

A Type I condition is a subsurface or latent physical condition that differs materially from what the contract indicated, such as rock where the borings showed soil. It is judged against the contract documents.

What is a Type 2 differing site condition?

A Type II condition is an unknown physical condition of an unusual nature that differs materially from what is ordinarily encountered in that type of work. It is judged against normal industry experience, so it is usually harder to prove.

How soon must you give notice of differing site conditions?

Check your contract. The federal clause requires written notice promptly and before the conditions are disturbed, and private contracts often set a specific number of days. Late notice is one of the most common reasons claims are denied.

Can you claim differing site conditions without a clause in the contract?

It is much harder. Without a clause, a contractor on a lump sum job generally carries the risk of unknown conditions, and recovery may depend on other legal theories. Ask a construction attorney before relying on one.

Keep site conditions tied to the job

Differing site conditions claims are won on records: the bid file, the notice, dated photos, daily reports and separate costs. CooperBuild AI keeps project chat, tasks and job records in one place, so a field photo and the follow-up about it stay attached to the job, and its assistants can pick up action items from the team's conversation. It includes built-in accounting with GL, AP and AR, connects to QuickBooks Online and supports integrated payments through Stripe.

Get started with a free trial of CooperBuild AI and keep every site condition on the job where your team can find it.