Eichleay Formula: How GCs Claim Home Office Overhead

Eichleay formula explained for GCs: the standby tests, how to calculate unabsorbed home office overhead, and how it works on private jobs.

Published
Reading time
7 min read
Author
Adam Hicks
On this page10 sections
  1. What does the Eichleay formula measure?
  2. Where does the Eichleay formula come from?
  3. Who qualifies for Eichleay damages?
  4. What breaks the standby test?
  5. How do you calculate the Eichleay formula?
  6. What are the weak spots in the formula?
  7. Does the Eichleay formula apply on private or state jobs?
  8. How do you protect a home office overhead claim?
  9. FAQ
  10. What is the Eichleay formula used for?
  11. What is the difference between home office overhead and field overhead?
  12. Do I need a written suspension order to use the Eichleay formula?
  13. Can the Eichleay formula be used between a GC and a subcontractor?
  14. Is the Eichleay formula accepted in every state?
  15. Keep the delay record tied to the job

By Adam Hicks, CooperBuild AI · November 18, 2026

The Eichleay formula is the method federal courts and boards use to price unabsorbed home office overhead when the government suspends or delays a construction contract. It allocates your fixed office costs to the delayed job by its share of company billings, turns that into a daily rate, and multiplies by the delay days. You only get to use it if you prove the delay was the owner's, it extended the job, and you were stuck on standby.

For a small or mid-size GC, the cost it chases is real: the office manager, the accountant, rent, insurance and your own salary keep running while a stalled job stops billing. This guide covers what the formula measures, the tests you must pass, how to run the math, and how it plays on private work.

What does the Eichleay formula measure?

It measures home office overhead that a delayed job should have carried but could not. In JMR Construction Corp. v. United States (Fed. Cl. 2014), summarized by Florida Construction Legal Updates (opens in a new tab), the court described home office overhead as accounting and payroll services, general insurance, upper-management salaries, utilities, taxes and depreciation: costs that benefit the whole business and cannot be charged to one job.

Contractors normally recover those costs through each job's billings. When the owner stops a job, that billing stream shrinks while the office costs do not. The shortfall is called unabsorbed home office overhead.

It is a different line from field overhead. The superintendent, trailer, temporary utilities and equipment on site are your general conditions, priced per day of extended duration. Eichleay covers only the office side.

Where does the Eichleay formula come from?

It is named for Eichleay Corp., a 1960 decision of the Armed Services Board of Contract Appeals (ASBCA No. 5183). The Federal Circuit has since relied on it as the standard for unabsorbed home office overhead on federal construction, and the court in JMR called it the sole method contractors can use to recover that cost against the government.

On fixed-price federal jobs, the usual route is the Suspension of Work clause at FAR 52.242-14 (opens in a new tab). If the contracting officer's act, or failure to act, suspends or delays the work for an unreasonable period, the clause calls for an adjustment for the added cost of performance, excluding profit.

Who qualifies for Eichleay damages?

The tests are strict. The Federal Circuit laid them out in P.J. Dick Inc. v. Principi, 324 F.3d 1364 (Fed. Cir. 2003) (opens in a new tab):

  1. Owner-caused delay with no concurrency. The government caused the delay, and no delay of yours or anyone else's ran at the same time. If both sides were late, see concurrent delay.
  2. The delay extended the job. The performance period ran longer, or you finished on time but had planned and been able to finish earlier.
  3. You were on standby. A written order that suspends all work for an uncertain period and requires you to stay ready settles this. Without one, you must show the delay had no set end, you had to be ready to return immediately at full speed, and you could not bill substantial work on the contract in the meantime.
  4. You could not take replacement work. Once you prove the first three, the government must show it was practical for you to pick up other work. If it does, you must prove you could not.

The court said only contractors who meet these "exacting requirements" are entitled to Eichleay damages. P.J. Dick lost on standby because it kept performing substantial work during the suspension.

What breaks the standby test?

Mostly, evidence that you were not really waiting. In JMR, the court threw out most of the claim period because the contractor had pulled its trailer, kept no crew or equipment on site, used a subcontractor to finish the remaining electrical work, and temporary fixes meant there was no urgency to return.

The P.J. Dick court also noted that if the owner gives you a reasonable time to remobilize after the suspension ends, you cannot be on standby. So a stop order with a known restart date, or a generous remobilization window, usually defeats the claim.

How do you calculate the Eichleay formula?

The formula has three steps. Every figure covers the same period, the job's actual performance period:

  1. Allocable overhead = (contract billings ÷ total company billings) × total fixed home office overhead.
  2. Daily rate = allocable overhead ÷ days of performance.
  3. Unabsorbed overhead = daily rate × delay days.

Here is a simple illustration with made-up numbers. A GC's 300-day federal job runs 360 days because of a 60-day written suspension. Over those 360 days the job bills $4,000,000, the company bills $20,000,000 total, and fixed home office overhead is $1,800,000.

Step Value
Allocation ratio ($4.0M ÷ $20.0M) 20%
Allocable overhead (20% × $1.8M) $360,000
Daily rate ($360,000 ÷ 360 days) $1,000
Unabsorbed overhead ($1,000 × 60 days) $60,000

Only fixed office costs belong in the pool. Job site costs already charged to the job stay out, and so does profit under FAR 52.242-14. Revenue recognized by job, the same number on your WIP report, is the usual input for billings.

What are the weak spots in the formula?

It assumes overhead tracks revenue, which is not always true. Vertex (opens in a new tab) points out it is especially hard to apply to a very small firm with one or two jobs: with only one active job, the formula assigns 100% of office overhead to it, even if the office was also chasing new work.

Expect the other side to attack what is in your pool. Variable costs, items already billed to the job, and costs outside the performance period are the usual targets.

Does the Eichleay formula apply on private or state jobs?

It depends on the state and the contract. New York's highest court rejected a mechanical use of the formula in Berley Industries v. City of New York (1978) (opens in a new tab), where the contractor offered no proof that its office costs actually went up. Florida's appellate court in Broward County v. Russell, Inc. (1991) (opens in a new tab) allowed it, as long as there is competent evidence of actual home office overhead damages. Outside the federal claims system, the D.C. Circuit in Williams Enterprises v. Sherman R. Smoot Co. (1991) (opens in a new tab) let a GC use the formula against its subcontractors for an 83-day delay, and applied it to an extended job, not only a suspended one.

The contract can also take it off the table. A no damages for delay clause may limit you to a time extension, and many standard general conditions include a mutual waiver of consequential damages that lists principal office expenses among the contractor's waived costs. Read both before you build a claim.

How do you protect a home office overhead claim?

Build the record while the job is stalled, not after:

  • Send written notice right away. Under FAR 52.242-14, costs incurred more than 20 days before written notice are not allowed, unless the claim comes from a written suspension order. See construction delay notice.
  • Ask for a written suspension order. It is the cleanest proof of standby.
  • Document standby daily. Who is on call, what equipment stays committed, what the owner told you about restart, and why you could not take other work.
  • Track monthly billings on the job. A sharp drop supports standby; steady billing defeats it.
  • Split office costs into fixed and variable each year, so the pool is ready when you need it.
  • Submit the claim in writing with an amount as soon as practicable, and no later than final payment.

FAQ

What is the Eichleay formula used for?

It calculates unabsorbed home office overhead when an owner, usually the federal government, suspends or delays a construction contract and the contractor's fixed office costs are left without enough job billings to absorb them.

What is the difference between home office overhead and field overhead?

Home office overhead is company-wide cost like office rent, accounting and executive salaries. Field overhead is job-specific cost like the superintendent, trailer and site utilities, usually priced separately as extended general conditions.

Do I need a written suspension order to use the Eichleay formula?

No, but it helps. A written order suspending all work for an uncertain period proves standby. Without one, you must show an indefinite delay, a duty to return immediately at full speed, and that you could not bill substantial work.

Can the Eichleay formula be used between a GC and a subcontractor?

Yes. In Williams Enterprises v. Sherman R. Smoot Co. (D.C. Cir. 1991), a GC recovered home office overhead from steel subcontractors whose negligence caused an 83-day delay. The subcontract's delay and damages clauses still control, so read them first.

Is the Eichleay formula accepted in every state?

No. Acceptance varies by state and contract. New York rejected a purely mechanical use without proof of actual damages, while Florida allows it with competent evidence of actual home office overhead damages.

Keep the delay record tied to the job

Whether an overhead claim holds up comes down to records: notices sent on time, standby logs, monthly billings and a clean split of office costs. CooperBuild AI keeps project chat, tasks, job costs and billing in one place, and its assistants can pick up action items, like "send written notice of the owner's stop order," from the team's conversation so they do not get lost. It includes built-in accounting with GL, AP and AR, connects to QuickBooks Online and supports integrated payments through Stripe.

Get started with CooperBuild AI and keep the paper trail behind every delay in the same place as the job.

Written by

Adam Hicks

Get started

Run your next job in Cooper.

Start on free credit and run a real job this week, or book a 30-minute demo on your own spec set, estimate or card statement. Either way, no card and no contract.

$20 in free credits, no card needed