- What is a pencil requisition in construction?
- How far ahead should you submit a pencil requisition?
- Do you include lien waivers with a pencil requisition?
- Can a pencil requisition still be rejected after approval?
By Adam Hicks, CooperBuild AI · November 23, 2026
A pencil requisition is an unsigned draft of your monthly pay application that you send the owner, architect or lender's reviewer a few days before the formal one. Everyone marks up the percent complete, stored materials and change orders while there's still time to fix them. Then you submit the signed pay app at the agreed numbers. Done well, a pencil requisition is the cheapest way to stop a pay app from being kicked back and missing the month.
GCs run the same process in the other direction too: subs send you their pencil drafts so you can agree their numbers before you roll them into your own billing. This guide covers both.
What is a pencil requisition?
A pencil requisition (also called a pencil draft, pencil copy or pencil draw) is a preview of the pay app you intend to submit. Procore's definition (opens in a new tab) is a "rough draft of a pay application" that gives the owner a preview of everything that will appear on the formal one. The name comes from the days when reviewers marked up a paper copy in pencil. Today it's usually a PDF, a spreadsheet or a draft in a billing portal.
The pencil uses the same schedule of values, the same math and the same change orders as the final. What it doesn't have is a signature, a notary stamp or lien waivers. Those come with the formal pay app.
Who requires a pencil requisition, and when?
Your contract decides. Many owners write a pencil step into the payment provisions or the specifications, and on cost-plus and GMP jobs it's especially common because the owner wants to check the numbers line by line.
Two public examples show the typical timing:
- New York City's Department of Design and Construction asks for the draft requisition ("pencil copy") at least one week before the end of the pay period (opens in a new tab). All parties meet to agree on work performed, including retainage, before the contractor submits the complete payment package.
- An owner-side construction attorney at Fletcher Tilton recommends that owners make the pencil step a condition (opens in a new tab) of submitting the formal application. His example gives the architect five to seven business days to review the draft.
If the contract is silent, ask at the preconstruction meeting. Some owners and lenders want a pencil every month even when the contract never mentions one. Put the pencil date, cutoff date and submission method in your calendar on day one.
What should a pencil requisition include?
Send the whole package you plan to bill, not a list of percentages:
- The schedule of values with this period's percent complete or quantities on every line, built the same way you'll back it up. Our schedule of values guide covers line structure.
- Approved change orders only. Pending changes are the first thing a reviewer strikes. Keep them tied to a change order log so the numbers match.
- Stored materials with invoices, delivery tickets, photos and proof of insurance or storage, if your contract allows billing for them. See stored materials billing.
- Retainage calculated the way the contract says, including any reduction you're asking for.
- Backup for the big movers: dated photos, quantity counts, daily reports and, on public work, certified payroll where required.
- A clear "DRAFT" or "PENCIL" label in the file name and on the document, so nobody processes it by mistake.
How does the pencil review work?
The usual sequence on a monthly cycle looks like this:
- Collect sub pencils first. Set your subs' pencil date several days before yours. One GC on r/Construction asked (opens in a new tab) why subs kept billing late; a top reply said contracts required billings by the 20th but they kept arriving at month-end.
- Walk the job. The PM and superintendent compare each sub's percent complete with what's actually installed. A commenter in another r/Construction thread (opens in a new tab) described exactly this: the sub submits a pencil req, you reconcile it on site, then the sub submits the real one.
- Roll it up. Combine the agreed sub numbers with your own self-performed work, general conditions and fee into your pencil to the owner.
- Send it to the reviewers. That might be the architect, the owner's rep, a construction manager or a lender's inspector. Ask for one consolidated markup, not three sets of conflicting comments.
- Meet or call on the disputed lines. Bring the backup. Settle each line with a number and a reason.
- Confirm in writing. Send one email listing the final number for every line that changed.
- Submit the formal pay app at the agreed numbers, signed and with lien waivers and any other required documents, by the cutoff.
On lender-financed jobs the pencil often lines up with the draw inspection. Our construction draw schedule guide explains how lender draws fit around your billing.
What should you do when lines get marked down?
Not every cut is wrong, so sort them:
- The work isn't there yet. Accept it and bill it next month.
- It's a timing issue. Pencils often project work through the end of the period. If the reviewer doubts it'll be in place, agree on what you'll show by period end.
- You can prove it. Send a dated photo, a quantity takeoff of installed work or a delivery ticket the same day. A markup answered two days later usually stands.
Ask for a reason on every cut. "Reduce to 25%" isn't a reason. "Only one of four units is set" is, and it tells you what to show next time.
Keep your own record of every line where you still believe more is earned: the line, your number, the agreed number and the reviewer's reason. If underbilling becomes a pattern, it shows up on your WIP report and in your cash flow.
Does agreeing to a pencil requisition waive your rights?
Generally it shouldn't, but read your contract. Procore notes that even an approved pencil doesn't guarantee the formal pay app is paid. Missing lien waivers or late changes can still get it rejected. Some contracts spell it out: one sample pencil draw clause (opens in a new tab) describes the meeting as an effort to resolve disagreements and says the contractor reserves all its rights when the formal application is processed.
If you accept a cut you disagree with, say so in your confirmation email and bill the line again next month with better backup. If the dollars are large, talk to your attorney before you sign anything that reads like a release.
How do you keep pencil and final pay apps in sync?
Trouble starts when the pencil and the formal pay app drift apart: someone edits one spreadsheet and forgets the other, or a change order sneaks in after the review. A few habits help:
- One source of numbers. Build the formal pay app from the agreed pencil, not from a fresh copy of last month's file.
- Version everything. Save the marked-up pencil, the agreed version and the final, with dates. Procore recommends keeping that version history so markups aren't lost when a digital file gets overwritten.
- Lock the period. Once the pencil is agreed, hold new changes for next month unless the reviewer agrees in writing.
For the sub side of the same review, see our subcontractor pay application review checklist.
Where CooperBuild AI fits
The pencil process gets painful when the schedule of values lives in one spreadsheet, change orders in another, sub billings in email and costs in QuickBooks. CooperBuild AI is an AI-native operating system for general contractors. The estimate becomes the live project, and the schedule of values, change orders, vendor bills, pay apps and job costs hang off the same line items. CooperBuild AI includes built-in accounting (GL, AP and AR), connects to QuickBooks Online and supports integrated payments through Stripe.
If your monthly billing still means reconciling three versions of the same numbers, start a 14-day free trial (opens in a new tab) and run your next pay app from the job itself.
FAQ
What is a pencil requisition in construction?
A pencil requisition is an unsigned draft of a monthly pay application that a contractor sends to the owner, architect, construction manager or lender's reviewer before the formal submission. Reviewers mark up percent complete, stored materials and change orders so the formal pay app goes in at agreed numbers.
How far ahead should you submit a pencil requisition?
Follow your contract. Many projects set the pencil date about five days to a week before the formal pay app is due; New York City's Department of Design and Construction, for example, asks for the draft at least one week before the end of the pay period.
Do you include lien waivers with a pencil requisition?
Usually not. Lien waivers, signatures and notarization normally come with the formal pay application, after the numbers are agreed. Check your contract for any documents the owner wants with the draft.
Can a pencil requisition still be rejected after approval?
Yes. An agreed pencil sets expectations, but the formal pay app can still be rejected if its numbers differ from the pencil, a change order was added late, or required documents such as lien waivers are missing.
This article is general information, not legal or financial advice. Payment terms and pencil requirements vary by contract, owner, lender and state; confirm specifics with your contract and attorney.