On this page8 sections
- What is a pass-through claim in construction?
- Why do GCs pass sub claims through instead of paying them?
- What is the Severin doctrine and why does it matter?
- What should a liquidating agreement include?
- How should a GC review a sub's claim before passing it through?
- What mistakes leave the GC liable for the sub's claim?
- FAQ
- What is a pass-through claim?
- What is a liquidating agreement in construction?
- Can a subcontractor sue the owner directly?
- Does a GC have to pass through a sub's claim?
- Keep the claim record on the job
By Adam Hicks, CooperBuild AI · November 26, 2026
A pass-through claim is a subcontractor's claim against the owner that the general contractor presents in its own name, because the sub has no contract with the owner. The GC acts as a conduit: it carries the sub's extra-work or delay costs up the chain, and the sub's recovery usually depends on what the owner pays. Done right, it is backed by a written liquidating agreement and the GC's own notice deadlines are met.
This guide covers when to pass a claim through, what the agreement should say, how to check the sub's numbers, and the mistakes that leave the GC holding the bill.
What is a pass-through claim in construction?
Most subcontractors have no contract with the owner. Lawyers call that a lack of privity, and it usually means the sub can't sue the owner for breach of contract directly (Peckar & Abramson (opens in a new tab)).
So when the owner causes the sub's extra cost, through a design error, a late site area or an owner-driven delay, the claim has to travel through you.
It isn't a change order. A change order is agreed scope and price; a pass-through claim is what's left when the owner says no and the sub still believes the owner owes it.
Why do GCs pass sub claims through instead of paying them?
Because the GC often isn't the one at fault, and the money it would pay the sub is money it would have to recover from the owner anyway.
It also avoids fighting two cases at once, where you argue the owner caused the delay while the sub argues you did. Peckar & Abramson notes a liquidating agreement keeps your position consistent and defers the sub dispute until the owner dispute is resolved.
As one MEP manager at a large GC put it on r/ConstructionManagers (opens in a new tab), prompt, documented impact notices from subs are what help "the GC make a case for you to the owner."
What is the Severin doctrine and why does it matter?
On federal work, Severin v. United States (Ct. Cl. 1943) held a prime couldn't recover its sub's costs because it couldn't show it was liable to the sub for them.
Later cases narrowed it. In E.R. Mitchell Construction Co. v. Danzig (Fed. Cir. 1999), the court explained that the government carries the burden to prove the prime isn't liable, and it takes "an iron-bound release or contract provision immunizing the prime contractor completely from any liability to the sub" (CourtListener (opens in a new tab)). Conditional liability, where the GC owes the sub only "as and when" it is paid by the owner, does not bar the claim.
The lesson: don't release the sub's claim against you completely. Limit your liability to what you recover from the owner. State rules on private work vary, so check with counsel.
What should a liquidating agreement include?
A liquidating agreement (also called a pass-through agreement) is the contract between you and the sub that sets the rules for the claim. Peckar & Abramson notes there is no set form, but it should be clearly spelled out, and a general flow-down clause or a pay-when-paid clause usually isn't enough on its own.
Points GCs commonly cover, drawn from Peckar & Abramson's two articles on the topic:
- The claim itself. Describe the sub's claim and the owner's denial.
- GC liability limited to recovery. You owe the sub what the owner pays on its claim, and nothing more, while staying conditionally liable so the claim survives.
- No other claims. The sub confirms it has no other claims against you on this issue.
- Who pays to pursue it. The sub carries the cost of preparing and presenting its part, and assists at its own expense.
- Indemnity. The sub indemnifies you for counterclaims and costs tied to its claim.
- Standstill. The sub won't sue or arbitrate against you until the owner dispute is resolved, and any case it filed is paused.
- Bound by the outcome. The sub accepts any result that binds you.
- Settlement authority. You decide whether and when to settle, and how proceeds are split.
Peckar & Abramson recommends a strong pass-through clause in the subcontract up front, because by the time a dispute hardens, the sub may not agree to anything.
How should a GC review a sub's claim before passing it through?
Treat the sub's claim like your own, because to the owner it is. A padded sub claim can taint the owner's view of the rest of your claim.
- Check notice and timing. Did the sub give you notice on time under the subcontract, so you could give the owner notice on time under the prime contract?
- Tie cost to cause. Every dollar should trace to an owner-caused event: an RFI response, a directive, a late site area, a design revision.
- Separate the sub's own problems. Remove costs from the sub's own productivity issues, bid errors or delays it caused.
- Check the schedule logic. For delay costs, ask for an analysis that ties the event to the critical path. Our guide to time impact analysis shows what that looks like.
- Apply the prime contract's pricing rules for markup and rates.
- Add your own costs. Your extended general conditions may belong in the same claim.
On federal contracts, a claim over $100,000 must be certified that it is made in good faith and that the supporting data are accurate and complete to the best of the signer's knowledge (FAR 33.207 (opens in a new tab)). The CMAA paper on proving and pricing subcontractor delay claims (opens in a new tab) warns that primes who certify a sub claim to a public owner take on False Claims Act risk. So review it; don't just forward it.
What mistakes leave the GC liable for the sub's claim?
- Missing your own deadlines. ASCE warns that a GC who misses the notice provisions in its prime contract can doom a valid sub claim and face exposure to the sub (ASCE (opens in a new tab)). Give the owner timely notice with a proper construction delay notice.
- Promising and then sitting on it. In Rad and D'Aprile v. Arnell Construction (N.Y. trial court), the GC agreed in a letter to include the sub's delay costs in its claim to the city, then filed after the prime contract's time limit and settled without the sub. The court found the GC liable for breaching its duty of good faith, and held the letter was a liquidating agreement that overrode the sub's no-damages-for-delay clause (Bradley (opens in a new tab)).
- Settling without the sub. ASCE flags this as a common source of GC liability.
- No written agreement. Without a limit tied to owner recovery, a sub that gets only part of its claim from the owner may come after you for the rest (Peckar & Abramson).
- Ignoring the subcontract. A no damages for delay clause or pay-if-paid clause shapes the claim, and later letters can change it.
This article is general information, not legal advice. Pass-through rules depend on your contracts, the owner (public or private) and state law, so confirm your approach with a construction attorney.
FAQ
What is a pass-through claim?
A pass-through claim is a subcontractor's claim against the owner that the general contractor presents in its own name, because the sub has no contract with the owner. The sub's recovery usually depends on what the owner pays.
What is a liquidating agreement in construction?
A liquidating agreement is a written deal between a GC and a sub that lets the GC pass the sub's claim to the owner. It usually limits the GC's liability to what it recovers and sets costs, cooperation and settlement rules.
Can a subcontractor sue the owner directly?
Usually not for breach of contract, because the sub has no contract with the owner. Mechanics liens and payment bonds are separate remedies with their own rules.
Does a GC have to pass through a sub's claim?
It depends on the subcontract. Many subcontracts include a pass-through clause, and a later letter or agreement can create that duty. Once you agree to do it, pursue the claim on time.
Keep the claim record on the job
A pass-through claim is won on dates: when the RFI went out, when the directive came back, when the sub gave notice and when you told the owner. CooperBuild AI is an AI-native operating system for general contractors, built on one idea: the estimate is the company. When a proposal is approved, the estimate becomes the live project, and subcontracts, change orders, pay apps, payments and the general ledger hang off the same deliverables. It has built-in accounting (GL, AP and AR), connects to QuickBooks Online, and takes payments through Stripe. Stop stacking Procore, QuickBooks and a spreadsheet to rebuild a claim after the fact.
If you want the claim history and the job cost on one record, start a 14-day free trial (opens in a new tab).